1
At 1 .20 p .m.
2
on March 23rd, 2005, a massive explosion and fire erupted at the BP refinery in Texas City, Texas.
3
The explosion killed 15 workers and injured 180 others, many of them seriously.
4
The blast occurred at the isomerization, or ISOM, unit, which produces materials to boost the octane rating of gasoline.
5
The explosion shattered windows in homes and businesses up to three -quarters of a mile away from the 1 ,200 -acre refinery.
6
As thick black smoke billowed from the plant, authorities instructed some 43 ,000 Texas City residents to stay indoors.
7
The accident cost BP billions of dollars in victims' compensation, property damage, and lost production.
8
This investigation was the largest and most comprehensive investigation in the history of the Chemical Safety Board.
9
CSB Supervisory Investigator Don Holmstrom led a two -year investigation to determine the root causes of the accident.
10
We interviewed over 370 witnesses.
11
We looked at thousands of documents, literally millions of pages of documents, and we examined the plant,
12
inspected over 40 pieces of instrumentation and equipment.
13
The investigation team examined a wide range of safety systems,
14
practices, and standards, and looked at human factors such as fatigue and communication between operators.
15
The board's report was released at a public meeting in Texas City on March 20, 2007.
16
Then -CSB chairman Carolyn Merritt presided.
17
MANY OF YOU HERE TONIGHT HAD FAMILY MEMBERS OR CO -WORKERS WHO WERE VICTIMS OF THIS EXPLOSION.
18
TO ALL OF YOU, I EXPRESS MY DEEPEST CONDOLENSES AND SINCERE WISHES THAT SOCIETY NEVER ALLOWS ANOTHER ACCIDENT LIKE THIS TO OCCUR.
19
THE TRAGEDY AT BP WAS THE WORST INDUSTRIAL ACCIDENT IN THE UNITED STATES IN NEARLY 15 YEARS.
20
THE CSB CONCLUDED THAT IT WAS THE RESULT OF ORGANIZATIONAL and safety deficiencies at all levels of the company.
21
We found that BP management had, for many years, overlooked warning signs of a possible catastrophic accident.
22
There's an old saying that if you think safety is expensive, try an accident.
23
Accidents cost a lot of money, and they're not only in damage to plant and in claims for injury,
24
but also in the loss of the company's reputation.
25
The reason why the Texas City accident has such an impact is because when people look at it,
26
they can see that they are all in the same boat,
27
that the problems which led to that accident are likely to be present at other sites around the world.
28
My fear is that some of the other refineries within the United States will feel
29
that couldn't happen to me and the ones that feel that
30
that couldn't happen at their site is the ones that are set up to have it happen there.
31
The following CSB computer animation depicts the sequence of events over
32
an 11 -hour period leading to the explosion at the BP Texas City Refinery on March 23, 2005.
33
Several units at the Texas City Refinery had been shut down for lengthy maintenance projects,
34
which required nearly 1 ,000 contractors to be on -site along with BP employees.
35
BP had positioned a number of portable trailers close to process units for the use of contractors and other maintenance workers.
36
Over a period of months, BP had located 10 trailers for workers servicing the Ultracracker unit,
37
including a double -wide wood frame trailer that contained 11 offices and was regularly used for meetings.
38
Though these trailers were located near the isomerization unit, the occupants were not warned the ISOM unit was about to start up,
39
a potentially hazardous operation.
40
At 2 .15 a .m on March 23rd, overnight operators began introducing flammable liquid hydrocarbons known as raffinate into
41
a 170 -foot tall raffinate splitter tower used to distill and separate gasoline components.
42
Near the base of the tower, there was a single instrument that measured how much liquid was inside.
43
It transmitted this information to a central control room located away from the ISOM unit.
44
But this level indicator was not designed to measure liquid above the nine -foot mark.
45
During normal operation, the tower was only supposed to contain about six and a half feet of liquid.
46
But during start -ups, operators routinely deviated from written procedures and filled the tower above the nine -foot mark,
47
concerned that if the liquid level fluctuated too low, it would cause costly damage to the furnace.
48
At 3 .09 a .m., as the liquid neared the eight -foot mark, a high -level alarm activated and sounded in the control room
49
but a second high level alarm slightly further up the tower failed to go off by 3 30 a .m.
50
the level indicator showed that liquid had filled the bottom nine feet of the tower
51
and the feed was stopped the CSB later estimated
52
that the liquid was in fact at a height of 13 feet
53
but operators could not know the actual level because the indicator only measured up to nine feet.
54
The lead operator had been overseeing the startup from a satellite control room within the ISOM unit.
55
At 5 a .m., he briefly updated the night board operator in the central control room about the startup activities.
56
The lead operator then left the refinery early, an hour before the end of the shift.
57
A new board operator arrived in the control room around 6 a .m.
58
to start his 30th day in a row working a 12 -hour shift.
59
He spoke briefly with the departing night shift operator and then read the logbook to prepare for the startup.
60
But the logbook did not clearly indicate how much liquid was already in the tower and equipment,
61
and it left no instructions on routing of the liquid feed and products when the startup resumed.
62
Instead, the control board operator only found a one -line logbook entry that said, ISOM brought in some RAF to unit to pack RAF with.
63
At 7 .15 a .m., the day shift supervisor arrived.
64
Because he was more than an hour late, he received no formal briefing from personnel on the night shift about conditions in the ISOM unit.
65
At 9 .51 a .m., operators resumed the startup.
66
They began recirculating the liquid feed and adding more liquid to the already overfilled tower.
67
As new feed was added, startup procedures called for regulating the liquid level in the tower using the automatic level control valve.
68
But the board operator and others had received conflicting instructions on routing the product.
69
As a result, this critical valve was left closed for several hours, blocking the flow of liquid from the tower.
70
A few minutes later, operators lit burners on the furnace to begin heating up the feed, part of the normal start -up process.
71
While the start -up was underway, the day supervisor left the refinery on short notice just before 11 a .m.
72
to attend to a family medical emergency.
73
Contrary to BP's own procedures, no experienced supervisor was assigned to replace him.
74
This left a single control board operator, now without a qualified supervisor, to run three refinery units,
75
including the ISOM unit, which needed close attention.
76
The refinery had eliminated a second board operator position following corporate budget cuts in 1999 after BP acquired Amoco.
77
As the start -up continued, the tower steadily filled with liquid, reaching a height of 98 feet shortly before noon,
78
more than 15 times the normal level.
79
But the improperly calibrated level indicator told operators in the control room
80
that the liquid was at 8 .4 feet and gradually falling.
81
Furthermore, the control panel was not configured to clearly warn operators of the growing danger.
82
It did not display flows into and out of the tower on the same screen, nor did it calculate the total liquid in the tower.
83
Meanwhile, the maintenance contractors, who were not involved in the operation of the ISOM unit, left their work trailers to attend a company lunch,
84
celebrating a month without a lost time injury.
85
At 12 .41 p .m., an alarm activated as the rising liquid compressed the gases remaining in the top of the tower.
86
Unable to understand the source of the high pressure, operators opened a manual chain valve to vent gases to the unit's emergency relief system,
87
a 1950s -era blow -down drum that vented vapor directly into the atmosphere.
88
Operators also turned off two burners in the furnace to lower the temperature inside the tower, believing this would reduce the pressure.
89
Nobody knew the tower was dangerously full.
90
The operators did become concerned about the lack of flow out of the tower
91
and began opening the valve to send liquid from the bottom of the tower to storage tanks.
92
But this liquid was very hot as it flowed through the heat exchanger
93
it suddenly raised the temperature of the liquid entering high up the tower by 141 degrees fahrenheit
94
it was now about 1 p .m contract workers unaware of the startup
95
and the looming danger returned from lunch
96
and began a meeting in the double wide trailer in the corner room closest to the blowdown drum
97
over the next few minutes the hot feed entering the tower caused the liquid inside to start to boil and swell.
98
Liquid filled the tower completely and began spilling into the overhead vapor line, exerting great pressure on the emergency relief valves 150 feet below.
99
At 1 .14 p .m., the three emergency valves opened,
100
sending nearly 52 ,000 gallons of flammable liquid to the blowdown drum at the other end of the ISOM unit.
101
Liquid rose inside the blowdown drum
102
and overflowed into a process sewer setting off alarms in the control room
103
but the high -level alarm on the blowdown drum failed to
104
go off none of the operators knew of the catastrophe unfolding
105
in the ISOM unit as flammable hydrocarbons overfilled the blowdown drum operators nearby saw a geyser of liquid
106
and vapor erupt from the top of the stack the equivalent
107
of nearly a tanker truck full of hot gasoline fell to the ground
108
and began forming a huge flammable vapor cloud
109
this scene based on csv computer modeling shows how the vapor
110
cloud expanded in just 90 seconds engulfing the unit in the
111
nearby trailers full of workers about 25 feet from the base
112
of the blowdown drum two workers were parked in a pickup truck with the engine idling
113
As flammable vapor entered the air intake, the diesel engine began to race.
114
The two workers fled, unable to shut off the engine.
115
Moments later, witnesses saw the truck backfire and ignite the vapor cloud.
116
Powerful explosions swept through the area.
117
Computer modeling shows how the blast pressure wave accelerated through the ISOM unit, causing heavy destruction and igniting fires throughout the area.
118
The workers inside the trailers were right in the path of the explosions.
119
The fires continued to burn for hours.
120
Twelve of the 20 occupants of the double -wide trailer were killed, along with three workers in a trailer nearby.
121
Dozens of others suffered serious burns, fractures, and other traumatic injuries.
122
The wood and metal frame trailers were blown apart by the blasts.
123
Firefighters struggled to rescue the injured and recover the victims.
124
Fifty large chemical storage tanks were damaged, and the ISOM unit remained shut down for more than two years.
125
During the early stages of our investigation, our team had noted there were multiple safety system deficiencies at the Texas City plant.
126
We also found there was a history of fatalities of the plant.
127
Prior to the March 2005 accident, 23 people died in accidents over a 30 -year period at the Texas City refinery,
128
beginning when it was owned by Amoco and continuing after BP acquired the refinery in 1999.
129
The CSB wanted to know what the connection was between this history of fatal incidents and organizational and cultural factors.
130
BP Corporation's lack of focus on preventing major accidents allowed budget cuts to be made without assessing the impact on process safety.
131
The CSB found that cost -cutting,
132
production pressures, and failure to invest significantly impacted the process safety performance at the Texas City refinery
133
and left the refinery vulnerable to catastrophe.
134
After the merger with Amoco, BP ordered a 25 % reduction in fixed costs at all its refineries.
135
This impacted important process safety systems such as staffing, training, and mechanical integrity.
136
The effects of the budget cuts became apparent in a number of internal BP documents made public following the accident.
137
In one, the refinery manager was quoted as having observed in 2002 that the infrastructure at Texas City was in complete decline.
138
He ordered a study of the refinery's safety and mechanical integrity, a study which was shown to BP executives in London.
139
That study warned of serious concerns about the potential for a
140
major site incident following more than 80 hydrocarbon releases in the previous two years.
141
The study also concluded that its own findings were urgent and far -reaching.
142
A follow -up BP study in 2002 found the refinery's integrity
143
and reliability issues were clearly linked to the reduction in maintenance spend over the last decade.
144
In 2003, a maintenance assessment stated that cost -cutting measures have intervened with the group's work to get things right.
145
Usually reliability improvements are cut.
146
And later that year, a company audit found the current condition of the infrastructure and assets is poor at Texas City,
147
and that maintenance spending was limited by a checkbook mentality.
148
Only the money on hand would be spent, rather than increasing the budget.
149
In March 2004, BP auditors in London concluded that 35 business units around the world, including the Texas City refinery,
150
suffered from a host of common safety problems,
151
including widespread tolerance of noncompliance with basic HSE or health safety and environmental rules,
152
poor implementation of safety management systems, and lack of leadership, competence, and understanding.
153
There were a number of reports
154
that were coming up to as high as the board level that indicated serious problems throughout the BP system.
155
During 2004, the Texas City refinery had three major accidents.
156
In addition to this process unit fire that caused $30 million in damage, two other accidents in 2004 resulted in three fatalities.
157
Yet this same year, the refinery had its lowest ever recordable injury rate, a statistic that does not include fatalities.
158
The CSB found that maintenance spending increased between 2003 and 2004,
159
but most of the increases were for responding to serious accidents and complying with environmental requirements, not for preventive maintenance.
160
Late in 2004, the Texas City refinery manager made a presentation to supervisors titled
161
Safety Reality, reviewing fatalities at the plant over the past 30 years.
162
One of the slides was entitled, Texas City is Not a Safe Place to Work.
163
BP did its own safety culture survey that was done just prior to the accident.
164
That survey indicated there was an exceptional degree of fear among employees of a major catastrophe.
165
Among the findings of the survey, the pressure for production, time pressure, and understaffing are the major causes of accidents at Texas City.
166
Critical events, like failures or breakdowns, are generally not attended to.
167
Production and budget compliance gets recognized and rewarded above anything else.
168
Sociology professor Dr. Andrew Hopkins has written extensively on the causes of industrial disasters.
169
My feeling is
170
that the solution to this problem of cost cutting by senior
171
people is to hold them responsible for the safety implications of those cost cuts, so that when they order a cost cut,
172
they should personally be able to certify that these things will not have adverse safety consequences.
173
The Safety Culture Survey also pointed to the exceptionally high executive turnover at the refinery.
174
Six different business unit leaders, or BULs, in seven years prior to the accident.
175
The authors of the survey report concluded,
176
we have never seen an organization with such a history of leadership changes over such a short period of time.
177
Many managers are in and out within a space of two years,
178
And what they are assessed on the basis of is the profit they make on an annual basis.
179
Now, as a manager, am I going to spend a large amount of money to deal with some remote risk
180
that is very unlikely to generate a major accident during my year or two on my watch here?
181
The survey of Texas City employees also found concern about safety and equipment checks potentially left undone.
182
There was a check -the -box mentality, which indicated that personnel would go through the motions with various policies and procedures,
183
but the work would not be conducted. For example,
184
the tower high -level alarm had been reported as not functioning several times in the two years prior to the accident.
185
But maintenance work orders for this alarm were closed, although the repairs were never actually made.
186
Work orders could be closed out as completed, even though the work hadn't been performed.
187
This is important because we found that on the day of the incident during the ISOM startup,
188
there were a number of instruments and equipment that were not functioning properly.
189
On February 20, 2005, a company safety manager wrote, I truly believe we are on the verge of something bigger happening.
190
Then, three weeks later, a BP business plan recognized a number of key safety risks,
191
including that TCS or Texas City site kills someone in the next 12 to 18 months.
192
Eight days later, those fears were realized.
193
Here were these warnings.
194
These audits were sounding very clear warnings.
195
So why weren't they attended to?
196
I think my feeling is that Texas City was virtually paralyzed by the cost cutting which had occurred at that site.
197
And they were simply unable to respond to those warnings.
198
There needs to be somebody on the board of directors who can interpret their reports
199
and be in position to drive change effectively.
200
The CSB's final report recommended
201
that BP appoint an additional non -executive member of the Board of Directors with specific expertise in refinery operations and process safety.
202
So the problem at Texas City was that they were essentially blind to this issue of process safety.
203
They were focusing on personal safety.
204
The CSB concluded that over a period of years, BP managers focused on lowering rates for personal injuries, such as slips, trips, and falls,
205
while often disregarding key process safety indicators.
206
We as members of the traveling public intuitively understand
207
that the numbers of baggage handling injuries really tells us nothing about the likelihood of a major accident,
208
an aircraft crash, and no airline in its right mind is going to try
209
and convince the traveling public of how safe it is by telling you about its workforce injury statistics.
210
Dr. Trevor Kletts is an internationally recognised chemical process safety expert.
211
Process safety deals with the fires and explosions and toxic releases and things like that.
212
And you can have a very good accident rate for what we call hard -hats accidents, but not for process ones.
213
There are a whole series of incidents occurring at BP in the years prior to the accident gas releases, other kinds of releases, fires,
214
all of which were telling you that process safety was not well -managed.
215
You need to measure process safety performance with the appropriate indicators, both leading and lagging indicators.
216
Lagging indicators measure events that have already occurred, such as fires, explosions, and equipment failures.
217
Leading indicators are designed to predict the likelihood of an accident before it occurs.
218
For example, the percentage of equipment inspections that are overdue.
219
The opening of a safety release pressure relief valve is itself an indicator that things are not as they should be.
220
So we should count those and try and reduce the number of occurrences of those sorts of events.
221
But the investigation found that BP did not effectively use leading and lagging indicators to measure and drive process safety performance.
222
For example, BP's pay plan rewarded managers primarily for controlling costs.
223
The only safety metric used to calculate bonuses was the personal injury rate.
224
Process safety was not considered.
225
The CSB final report recommended that the United Steelworkers Union
226
and the American Petroleum Institute create a new standard for process safety indicators for the petrochemical industry.
227
The board also called on BP to use leading and lagging indicators to strengthen refinery safety performance.
228
After an accident, managers often say, I didn't know this was happening, or not happening, as the case may be.
229
If I'd known, I'd have stopped it.
230
Now, this is bad management.
231
It's the manager's job to know what is going on.
232
And he can do that by going round and by keeping his eyes open and reading the accident reports in detail.
233
The CSB investigation noted that BP ignored numerous warnings of the potential for a catastrophic accident,
234
a result of not having an effective reporting and learning culture.
235
Glenn Irwin is a safety official with the United Steelworkers
236
and was a member of the independent panel that examined BP's safety culture.
237
I believe it's very important that we do have an open
238
and a trusting environment to where people can raise concerns
239
and they can tell management if they see a condition or something that is out of the ordinary.
240
BP's own internal audits, however, indicated a trusting environment was lacking. In 2005, the Texas City maintenance manager said in an email
241
that the refinery has a ways to go to becoming a learning culture and a way from a punitive culture.
242
it was a long -standing problem in 2000 the bp refinery
243
in grangemouth scotland had three serious incidents including a large process unit fire an investigation by the british health
244
and safety executive highlighted problems at the grangemouth refinery
245
that would show up again five years later in texas city there was need for corporate
246
and board oversight over process safety management there was a need to develop bleeding
247
and lagging indicators for process safety and there needed to be an emphasis on process safety in order to prevent major accidents.
248
But the CSB found little awareness in Texas City of the lessons BP executives promised would be learned worldwide after Grangemouth.
249
As British regulators concluded, BP's decentralized management structure impaired learning from previous incidents.
250
And the reason why BP failed to learn these lessons from other events, the reason why they seem to have this,
251
what I would call, learning disability, lies in the way in which the organization was designed.
252
It lies in the bonus systems of payment.
253
It lies in the decentralized structure of the organization.
254
It lies in the organizational location of process safety experts.
255
The CSB found that following the 1999 merger with Amoco, BP He dismantled AMACO's existing centralized safety structure.
256
The reorganization left a diminished process safety function that no longer reported to senior refinery leadership.
257
So I think the lesson, one of the lessons coming out of that, is that if an organization judges something important,
258
it will locate people towards the top of the apex in that organization, people with responsibility for that.
259
And the fact
260
that the process safety manager was further down the line is yet another indication of the lack of focus on process safety.
261
A positive safety culture would ensure that incidents are being reported, that they're being followed up on,
262
that there's enough resources to ensure adequate safety.
263
Over the years at Texas City, many critical incidents were not reported, nor were the lessons acted upon to prevent future catastrophic events.
264
And it's also in human nature there's a tendency to say, oh gosh, that was a near one, I'm glad that lead didn't catch fire,
265
let's forget about it and get on with the job.
266
For example, BP wasn't investigating abnormal conditions that were occurring repeatedly during startups at the ISOM unit.
267
The CSB examined 19 previous startups in the five years prior to the ISOM incident
268
and found in the vast majority of these startups, the operators ran a high level above the range of the level transmitter.
269
The problem with running the level above the reading is that you don't know how high the level really is.
270
This can lead to grossly overfilling the tower.
271
But even though high levels and pressures could have led to a catastrophic accident, the previous startups were never investigated as near misses,
272
and procedural deviations became accepted as normal.
273
The CSB investigation also found eight serious releases of flammable vapor from the ISOM blowdown drum,
274
two of which caught fire between 1994 and 2004.
275
Only three of the incidents were ever investigated.
276
Well, it's widely recognized now that you should investigate near misses, they're really near accidents, they're called near misses,
277
as thoroughly as you investigate accidents.
278
Well, it's only a matter of luck whether a leak of flammable liquid or gas catches fire or not.
279
In our final report, the CSB recommended
280
that BP's board of directors establish a system to encourage reporting of incidents without fear of retaliation, to investigate and implement prompt corrective actions,
281
and to communicate lessons throughout the company.
282
the first choice after an accident is to say how can we improve the design
283
so this can't happen how can we remove the opportunity for
284
errors even as releases occurred over many years in the isom
285
unit BP continued using equipment based on outdated designs the raffinate splitter tower lacked modern design safeguards,
286
such as redundant level indicators and alarms.
287
a differential pressure indicator, and automatic interlocks to prevent overfilling.
288
In a well -designed plant, a simple error like closing the road valve shouldn't result in an accident.
289
The design of the emergency pressure relief system was also outdated.
290
Relief valves vented hydrocarbons directly to the atmosphere through an antiquated blow -down drum, which was first installed in the 1950s.
291
The CSB report said the hydrocarbon should have been routed to an inherently safer disposal system,
292
such as a flare, to contain the hydrocarbon liquid and burn off flammable vapor.
293
In fact, the investigation found that Amoco's own safety standards, later adopted by BP, stated that new blowdown stacks,
294
which discharge directly to the atmosphere, are not permitted.
295
As facilities were upgraded, existing blowdown systems, which are still necessary, should be replaced.
296
Several occasions prior to the incident, BP had seriously considered connecting a flare to the ISOM unit.
297
In the early 1990s, when Amoco owned the refinery, three proposals were made to replace blow -down stacks at Texas City.
298
Two more proposals were made in 2002, after the merger with BP.
299
However, these decisions were impacted by production pressures and budget cuts,
300
and the flare was never constructed. In 1992, OSHA conducted an inspection at the Texas City refinery
301
because they had been released from a very similar blowdown drum in a different process unit.
302
OSHA cited the then Amoco refinery for the unsafe blowdown system.
303
OSHA determined that the design of the blow -down drum was unsafe because it did relieve the atmosphere.
304
It didn't relieve to a safe place.
305
But OSHA later withdrew the citation after Amoco asserted the equipment conformed to American Petroleum Institute standards.
306
In October 2006, the board issued a recommendation to the American Petroleum Institute calling for new guidelines
307
that warn against the use of blow -down drums similar to those found in Texas City.
308
We also recommended
309
that OSHA implement a national emphasis program for all oil refineries focused on the hazards of blow -down drums
310
that release to the atmosphere.
311
Whenever possible, companies should use inherently safer systems, such as flares, instead of blow -down drums.
312
The presence of occupied trailers near the blow -down stack added to the hazards of venting flammable material to the atmosphere.
313
Prior to the incident and prior to the startup of the ISOM unit, a number of trailers, occupied trailers,
314
have been placed close to the ISOM unit.
315
These trailers were occupied by workers who were not involved in the turnaround activities in the ISOM unit.
316
The investigation found this was a key factor leading to the deaths of the workers.
317
They were right on top of the process in trailers as close as 120 feet from the blow -down drum,
318
which is right at the edge of the isomerization process.
319
CSB investigator Mark Kasniak.
320
Well, it is not safe to have trailers
321
that close to a blow -down drum or at the edge of an active process in a petroleum refinery.
322
During an explosion in a refinery, you're actually safer in the open atmosphere than if you were working inside of a trailer.
323
This is because the explosion overpressure will destroy the weak trailer construction, resulting in the formation of missiles and walls collapsing,
324
which is potentially fatal to the occupants.
325
The CSB determined that industry sighting guidelines did not adequately protect trailer occupants from the fire
326
and blast damage that can occur hundreds of feet from an explosion like the one at BP.
327
We found that these guidelines were not safe enough prior to this accident and resulted in placing people in harm's way.
328
In addition, BP did not follow its own management of change procedures before placing most of the trailers in a dangerous location.
329
They did not assess the blast hazards posed to the trailer, and action items that were created during the review were never followed up and corrected.
330
Ultimately, the decision on where to place the trailers was largely based on convenience, not safety.
331
And contrary to BP startup procedures, on the morning of March 23rd,
332
managers did not remove personnel from the nearby trailers or even alert them that the potentially hazardous startup was taking place.
333
The explosion totally destroyed 13 trailers and damaged 27 others, some as far away as 1 ,000 feet.
334
People inside trailers as far away as 479 feet were injured.
335
In October 2005, the CSB issued an urgent recommendation to the American Petroleum Institute to revise industry standards
336
and establish minimum safe distances for occupied trailers away from hazardous process areas.
337
On June 21, 2007...
338
The American Petroleum Institute issued new industry guidelines to minimize the presence of people and occupied trailers in hazardous process areas.
339
For a long time, people were saying that most accidents were due to human error.
340
And this is true in a sense, but it's not very helpful.
341
It's a bit like saying that falls are due to gravity.
342
There were a number of human errors
343
that contributed to the overfilling of the tower and the disaster that followed at Texas City.
344
No one shows up to work planning to make mistakes, so we looked at the conditions in the workplace that would make error more likely.
345
You really need to look at why the operators did what they did.
346
CSB Human Factors Specialist Cheryl McKenzie.
347
There were a number of human factors issues involved with this incident, including fatigue of the workers,
348
training that was insufficient, and procedural deviations that occurred during the start -up.
349
The CSB investigation found that underlying conditions in the ISOM unit encouraged operators to consciously deviate from written operating procedures.
350
Why did they make that judgment?
351
I think they did because these procedures were, some of them were out of date, some of them were inapplicable.
352
They were routinely not following these procedures, and nobody had said otherwise.
353
Nobody had said, hang on, you must be following these procedures.
354
The investigation found that operators were concerned that
355
if they let the liquid level in the tower get too low during start -ups, it would damage the furnace.
356
So they had adopted an informal procedure of adding extra liquid to the tower during start -up.
357
To do this, they placed the level control valve in manual, not the automatic mode required by procedures
358
and left the valve closed to raise the liquid above the recommended six -and -a -half -foot level.
359
So routine had this practice become,
360
the CSB found that the tower's high -level alarm had activated 65 times during the previous 19 startups.
361
The outdated operating procedures for the unit did not establish any safe upper limit for the liquid level in the tower.
362
Unknown to operators, regularly overfilling the tower had serious risks.
363
The tower's liquid level transmitter had a limited range, and should the liquid rise above the maximum reading of 9 feet,
364
operators could not know if the tower was dangerously overfilling.
365
This informal practice of running the level in the Raffinate splitter tower above the range of the transmitter led to running blind.
366
They weren't aware of the dangers of overfilling the column,
367
And so they tended to err on the side of what they saw as caution by overfilling the column.
368
So their systematic deviation from what they should have been doing was actually well -intentioned.
369
It was with the interest of the company at heart that they were violating the start -up procedures.
370
But on the day of the accident, the routine deviation, overfilling the tower above the range of the indicator, coincided with a number of instrument failures,
371
which impaired the board operator's decision -making.
372
This had tragic results, as the board operator lost awareness of just how high the level was.
373
The tower level indicator had been calibrated for years based on 1975 data for a different liquid used in a different process.
374
As a result of the miscalibration, the indicator showed the level in the tower was declining just prior to the explosion.
375
when it was actually increasing.
376
And a backup high -level alarm on the tower failed to activate, seeming to confirm that the liquid level was dropping.
377
A sight glass on the tower was dirty and unreadable and could not be used to visually check the liquid level.
378
The investigation concluded that the board operator truly had no functional and accurate measure of the tower level on March 23, 2005.
379
And when the liquid finally did spill over into the blow -down drum, the high -level alarm there failed to go off.
380
BP procedures required that alarms and instruments and other equipment be checked for their functionality prior to startup.
381
The CSB determined that these checks were largely not performed.
382
A poorly designed computer display in the control room added to the difficulty of determining if the splitter tower was overfilling.
383
Liquid flows into and out of the tower were not shown on the same screen, even though the computer could have been configured to do so.
384
The investigation also found that communication problems among BP personnel during the morning of the startup increased the likelihood of errors.
385
Operators received contradictory instructions on where to send the products from the tower,
386
and the day shift operators never got clear information from the night shift about how much liquid the tower already contained.
387
Well, then the board operator and the other operators
388
that came in during the day shift really didn't understand what had occurred the night before,
389
so they're starting up this unit without full knowledge of the state of the unit, and they're making judgments and decisions based on incomplete information.
390
The investigation found that BP lacked adequate policies and a management emphasis on effective communications.
391
Key instructions on sending the feed into the tower were given over the phone and radio instead of in writing.
392
Operators later told investigators these verbal communications were rushed and vague.
393
Written communications in the logbook were brief and unclear.
394
Night shift operators did not conduct a crucial face -to -face
395
meeting to brief day shift operators on the conditions in the unit.
396
Therefore, they didn't realize how much liquid was in the tower and the equipment,
397
so they added more, which led to the subsequent overfilling of the tower, which later led to the release.
398
The opportunities for human error were multiplied by the lack of adequate supervision, staffing, and training at the refinery.
399
Training had been downsized, and that training was largely delivered through computerized means rather than face -to -face training.
400
BP did not train operators on the hazards of overfilling towers, and training for abnormal situations was insufficient.
401
Despite recommendations dating back five years, simulators were not used to train board operators on making critical decisions.
402
As noted in an internal BP email about simulators three weeks after the accident,
403
big pushback has always been initial cost.
404
Budget pressures also impacted control room staffing.
405
BP implemented a 25 % cost reduction in 1999.
406
During the same time period, BP downsized the board operators in the ISOM unit from 2 to 1.
407
Later, BP added an additional process unit to the responsibilities of the board operator and the ISOM unit.
408
The result was that you had three complex refinery units under the supervision of one board operator.
409
According to BP's own assessment, even under normal conditions,
410
monitoring and controlling these three units would require ten and a half hours of the board operator's 12 -hour shift.
411
But the startup of the ISOM unit would demand significantly more time and attention from the operator, whose workload was already nearly full.
412
And when the startup began to encounter problems late that morning, supervisory oversight of the board operator was absent.
413
BP's own policies required that a supervisor, or technically trained person, be present during startup because it's an especially hazardous period.
414
The supervisor who showed up on March 23rd left due to a family emergency, and there was no replacement.
415
Finally, investigators looked at the role operator fatigue played as a human factor contributing to the accident.
416
Fatigue can affect performance in many ways.
417
It can cloud decision -making.
418
It can delay responses to actions on a control board.
419
And it can lead an operator to miss out on what's going on overall in a unit.
420
Fatigue can impair judgment.
421
It can lead an operator to fixate on one operational parameter, such as a declining level, and lose track of other factors,
422
such as liquid being added to the tower for three hours and no liquid being removed.
423
ISOM unit operators had been working 12 -hour shifts for at least 29 days prior to the accident.
424
In particular, the board operator was likely suffering from fatigue, including acute sleep loss and a cumulative sleep debt of more than 43 hours.
425
We determined that BP had no fatigue prevention policy, and in fact there was no fatigue prevention policy in the industry as a whole.
426
Companies and employees may believe they benefit from overtime schedules, particularly during maintenance turnarounds, but operator fatigue can have deadly consequences.
427
Our final report recommended that the United Steelworkers
428
and the American Petroleum Institute develop new guidance on preventing fatigue in the petrochemical industry, including limits on hours and days at work.
429
OSHA's 1992 Standard on Process Safety Management,
430
or PSM, requires thousands of oil and chemical facilities to implement 14 management elements to prevent catastrophic releases.
431
The Environmental Protection Agency has similar requirements under its risk management program.
432
The CSB investigation revealed many long -standing deficiencies in the BP refinery's compliance with federal process safety regulations.
433
Preventive maintenance and testing procedures were inadequate for key alarms, instruments, and equipment.
434
Required safety studies of pressure relief systems were years overdue.
435
Operating procedures were out of date.
436
And there were other flaws.
437
Management of change reviews were not conducted for critical design, equipment, and procedural changes.
438
Hazard analyses were poor, overlooking serious fire and explosion risks.
439
Audits revealed many process safety problems, but they were never resolved.
440
OSHA's enforcement program for the PSM regulations requires planned,
441
comprehensive inspections of facilities with accident histories or other indications of catastrophic risks.
442
A 1992 OSHA directive stated the primary enforcement tool would be the Program Quality Verification Inspection,
443
or PQV, a large, complex audit involving highly trained OSHA inspectors and taking weeks or months to complete.
444
Despite the fact that the BP Texas City refinery had a long history of fatality incidents,
445
There was no program quality verification or intensive PSM inspection conducted at that refinery.
446
OSHA did conduct smaller, unplanned inspections of the Texas City refinery in response to accidents and complaints.
447
But these inspections did not uncover major flaws in process safety management compliance.
448
In fact, the CSB found that OSHA conducted only a handful of Program Quality Verification,
449
PQV inspections, at the thousands of regulated facilities across the country.
450
There's no set interval when OSHA comes in and inspects a plant in the United States.
451
We found that inspections in the U .S are largely driven by personal injury statistics.
452
The CSB also found that prior to March 2005,
453
the EPA never audited the Texas City Refinery for compliance with risk management requirements.
454
Other jurisdictions inspect process plants more frequently.
455
In California's Contra Costa County, a local process safety ordinance requires thorough inspections of 48 major oil
456
and chemical plants every three years by a team of specialized engineers.
457
In the United Kingdom, 105 specialists from the Health and Safety Executive inspect high hazard facilities every five years.
458
In addition, all nine refineries in the UK are inspected annually.
459
If accepted process safety principles had been thoroughly implemented at the refinery, this accident likely would not have occurred.
460
The CSB recommended that OSHA take steps to conduct more process safety inspections and strengthen enforcement of the PSM standard.
461
OSHA should identify those facilities at greatest risk, see that comprehensive inspections are conducted at such facilities,
462
and to establish the capacity to conduct those inspections, OSHA should create a group of highly trained PSM inspectors.
463
On June 12, 2007, OSHA announced a new national emphasis program to inspect most U .S oil refineries for process safety compliance.
464
I participated in the panel because I lost a near and dear friend in this incident.
465
A personal friend of mine was killed in this incident
466
and I thought it was very important that that the management systems be looked at with a fresh set of eyes.
467
Early in the investigation of the Texas City accident the CSB observed what appeared to be a pattern of safety deficiencies.
468
We We therefore issued an urgent recommendation, the first ever by this agency,
469
that BP convene an independent panel of experts to study the safety culture of its five
470
North American refineries.
471
In October 2005, BP established an 11 -member panel that included leading industry, labor, and academic safety experts.
472
It was headed by former
473
Secretary of State James A.
474
Baker III.
475
The panel found that BP did not ensure, as a matter of best practices,
476
that its management implemented a comprehensive and effective process safety management system.
477
The report, issued in 2007, concluded there were instances of a lack of operating discipline,
478
toleration of serious deviations from safe operating practices,
479
and apparent complacency toward serious process safety risks at each of BP's North American refineries.
480
The Baker panel also voiced concern that other companies share similar problems.
481
Ladies and gentlemen, we are under no illusion that such deficiencies are in fact limited to BP.
482
One of the things that I'd like to see personally after having served on the Baker panel
483
is that we will never have another incident of this magnitude, the number of people that were killed, the number of lives that were changed.
484
So many good, hard -working people go to work every day, and too often, some never return.
485
I think the work that we did in the Baker panel, I believe that if our work is applied within our industry,
486
we will not see another BP explosion.
487
The Baker panel report concluded that the restructuring following BP's merger with Amoco had resulted in a significant loss of people,
488
expertise, and experience in the refining sector.
489
Only much later did BP recognize the negative impact of these changes.
490
The CSB's final report said all hazardous chemical operations should be required to review the safety impact of major organizational changes.
491
The Board recommended that OSHA amend its Process Safety Management Standard to require management of change reviews for mergers,
492
acquisitions, personnel reductions, budget cuts or other organizational changes
493
that can impact process safety we also recommended
494
that the center for chemical process safety develop guidelines on how
495
to perform organizational management of change reviews the major problem with the chemical industry
496
and indeed with other industries is the way accidents are investigated, reports are written, circulated, read, filed away and then forgotten.
497
And then ten years later, even in the same company, the accident happens again.
498
There is a saying that organizations have no memory.
499
Only people have memory.
500
Once they leave the plant, the accident, the code there, is forgotten about.
501
And what companies must do in the petrochemical industry is realize
502
that the fact that you've had 20 years without a catastrophic event is no guarantee that there won't be one tomorrow.
503
You have to keep your eye on the ball constantly.
504
All oil and chemical businesses should seek to learn from the tragedy at BP.
505
The CSB believes there are key lessons to be drawn from our investigation.
506
The CSB said, managers, executives, and boards of directors should do the following.
507
Monitor Enter process safety performance using appropriate indicators.
508
Invest sufficient resources to correct problems.
509
Maintain an open and trusting safety culture where near misses are reported and investigated.
510
Ensure that non -essential personnel and work trailers are located a safe distance from hazardous process areas.
511
Ensure equipment and procedures are maintained and up to date.
512
Carefully manage organizational changes and budget decisions to ensure safety is not compromised.
513
Analyze and correct the underlying causes of human errors, including fatigue and miscommunication.
514
Finally, boards of directors must exercise their duty to ensure that the highest standards of safety are met.
515
The BP tragedy was years in the making, but it was by no means inevitable.
516
We hope our investigation will provide all of industry with valuable lessons to assure such a tragedy will not be repeated.
517
For the CSB's final report, key investigation documents, the Baker Panel Report,
518
and other information, please visit the Chemical Safety Board website at csb .gov.
519
BP cooperated with the CSB investigation and provided documents and witnesses voluntarily.
520
After the Texas City accident, BP acted to relocate trailers,
521
eliminate blow -down drums, and invest billions of dollars to upgrade the condition of its U .S refineries.
522
In 2007, BP accepted the recommendations of the Baker Panel, including a call to become a recognized industry leader in process safety management.
523
Thank you.
524
Thank you.

Download App

Everything you need to speak fluently

AI PronunciationScore every sentence
IPA PracticeMaster every sound
VocabularyBuild your word bank
Vocab GameLearn while playing

Same Channel

FOR YOU

Recommend Video

Vocabulary and speaking notes for this lesson

This C1 speaking lesson is built on the video “CSB Safety Video: Anatomy of a Disaster”. The speaker keeps coming back to these words: safety, process, operator, accident, tower. This video has 524 sentences and 7609 words to shadow. The speech runs for 54:40. The speaker talks at a steady 139 words per minute, a comfortable pace for shadowing. Only 78% of the words are among the 3,000 most common in English, so the vocabulary is demanding.

Key vocabulary in this video

The 15 most advanced words in the video, with pronunciation and meaning:

WordPronunciationMeaning
refinery noun/rɪˈfaɪnərɪ/A building, or a mass of machinery, used to produce refined products such as sugar, oil, or metals.
startup noun/ˈstɑɹtˌʌp/The act or process of starting a process or machine.
indicator noun/ˈɪn.dɪˌkeɪ.tə(ɹ)/A pointer or index that indicates something.
overfill verbTo fill beyond capacity or beyond what is appropriate.
blowdown nounThe removal of liquid and solid hydrocarbons from a refinery vessel by the use of pressure.
fatigue noun/fəˈtiːɡ/A weariness caused by exertion; exhaustion.
flammable adjective/ˈflæməbl̩/Capable of burning.
vapor noun/ˈveɪpɚ/Cloudy diffused matter such as mist, steam or fumes suspended in the air.
conclude verb/kənˈkluːd/To end; to come to an end.
catastrophic adjective/ˌkætəˈstɹɑfɪk/Of or pertaining to a catastrophe.
hazardous adjective/ˈhæ.zɚ.dɪs/Risky; dangerous; with the nature of a hazard.
organizational adjective/ˌɔː(ɹ)ɡənɪˈzeɪʃənəl/Of, relating to, or produced by an organization.
petroleum noun/pəˈtɹoʊliəm/A flammable liquid ranging in color from clear to very dark brown and black, consisting mainly of hydrocarbons, occurring naturally in deposits under the…
hydrocarbon nounA compound consisting only of carbon and hydrogen atoms.
supervisor noun/ˈsupɚˌvaɪzɚ/A person with the official task of overseeing the work of a person or group, or of other operations and activities.

Phrasal verbs you will hear

WordPronunciationMeaning
blow down verbTo knock over with an air current, most often wind.
start up verb/stɑɹˈtʌp/To rise suddenly.
go off verbTo explode.
follow up verbTo take further actions remaining after an event; to continue, revisit, or persist; especially, to maintain communication or verify.
blow apart verbTo destroy (something) by explosion or figuratively similar disasters (e.g. a scandal for a company).
burn off verbTo dissipate as the result of heat.
close out verbTo terminate; to call the end of.
come up to verbTo approach.

Grammar in this video

The structures the speaker uses most, with the exact words from the video:

StructureIn the video
Passive voice be + past participle — the focus is on what happens, not who does itwas released · are set · had been shut
Present perfect have/has + past participle — a past action that still matters nowhave intervened · has written · have never seen
Relative clauses who / which + clause — extra information about a person or thingones that are · study which was · drum, which was

Pronunciation to watch

The speaker uses 27 contractions and reduced forms, such as they're, didn't, I'd. Say them the short way, as you hear them.

  • The “th” sounds: strengthen /ˈstɹɛŋ(k)θən/, thoroughly /ˈθʌɹ.ə.li/
  • The “sh” and “zh” sounds: organizational /ˌɔː(ɹ)ɡənɪˈzeɪʃənəl/, deviation /ˌdiː.viˈeɪʃən/, deficiency /dɪˈfɪʃənsi/, recommendation /ˌɹɛkəmɛnˈdeɪʃən/, verification /ˌvɛ.ɹə.fɪˈkeɪ.ʃən/
  • Long words — get the stress right: refinery /rɪˈfaɪnərɪ/, indicator /ˈɪn.dɪˌkeɪ.tə(ɹ)/, catastrophic /ˌkætəˈstɹɑfɪk/, organizational /ˌɔː(ɹ)ɡənɪˈzeɪʃənəl/, supervisor /ˈsupɚˌvaɪzɚ/

How to practise with this video

  1. Listen to the whole video once without speaking and note the words you do not know.
  2. Shadow it sentence by sentence at normal speed, repeating each one until your rhythm matches the speaker.
  3. Record yourself and compare with the original, paying attention to words like refinery, startup, indicator.

What is the Shadowing Technique?

Shadowing is a science-backed language learning technique originally developed for professional interpreter training and popularized by polyglot Dr. Alexander Arguelles. The method is simple but powerful: you listen to native English audio and immediately repeat it out loud — like a shadow following the speaker with just a 1–2 second delay. Unlike passive listening or grammar drills, shadowing forces your brain and mouth muscles to simultaneously process and reproduce real speech patterns. Research shows it significantly improves pronunciation accuracy, intonation, rhythm, connected speech, listening comprehension, and speaking fluency — making it one of the most effective methods for IELTS Speaking preparation and real-world English communication.

Shadowing technique: read the full step-by-step guide →