Hey guys, Andy here with CQE Academy
2
and in today's video I want to talk about a really important topic which is the seven QC tools.
3
Now whether you just want to get better at work
4
and use these tools in your everyday job
5
or you're preparing for something like the green belt exam or the black belt exam or the CQE exam, today's lecture is for you.
6
All right, let's hit it with the computer and get started.
7
All right, let's go ahead and jump in right into the agenda.
8
So we're going to start with a brief intro of the seven QC tools, kind of talk about all of them and how they fit into the problem solving process or the improvement process.
9
And then we're going to go through each one.
10
We're going to start with the flow chart, the check sheet, the Pareto chart, the cause and effect diagram, scatter diagram, histogram, and then the control charts.
11
And then along the way, as we go through this, we're actually going to work a problem using all seven tools
12
and we're going to reduce the number of defects associated with our toaster.
13
All right, let's go and get started.
14
So the seven QC tools, I love this quote from Keoru Ishikawa who said,
15
as much as 95% of quality problems can be solved with seven fundamental tools.
16
And I absolutely agree with that.
17
I think these tools are probably the seven most powerful tools, whether you're talking about Greenbelt or Blackbelt or quality engineering, it doesn't matter.
18
These seven tools are incredibly powerful for solving problems and making improvements.
19
And this is a really important topic.
20
By the way, as we go through this, I'll make sure to talk about where we're at in something like the plan, do, check, act, or the DMAIC cycle.
21
We're going to solve a problem with our toaster, and we'll use either the DMAIC or the plan, do, check, act process to do it.
22
All right, let's get into it.
23
All right, so the very first tool is the flowchart.
24
And what a flowchart does is it's a visual tool that helps you depict the flow or the sequence of a process.
25
This could be things like the flow of information or the flow of tasks or material or people or decisions.
26
It doesn't matter.
27
The reason that a flowchart is
28
so incredibly valuable is it makes a really complex process simple and it promotes a common understanding of a process.
29
Anytime you get more than one person in a room to talk about a process, there's likely going to be disagreement about how the process works.
30
And I love using this analogy.
31
Oftentimes when we sit down to analyze a process, there's what management thinks is happening, There's what the procedure says is happening.
32
There's what's actually happening on the production floor.
33
And then there's what could be happening.
34
And the beauty of a flowchart is it does just that.
35
It gets everyone on the same page about what's actually happening.
36
And I love this quote from Dr. Deming who said, if you can't describe what you're doing as a process, you don't know what you're doing.
37
And the best way to describe what you're doing is to use a flowchart.
38
And that's why this tool is so powerful.
39
If you're in the planning phase or the define phase, it's really good to use a flowchart, define your process, and then use that flowchart to plan out your experiment
40
and plan out how you're going to make an improvement.
41
So let's do just that.
42
Let's say we're talking about our toaster and we want to make an improvement, right?
43
And so the first thing we're going to do is we're going to start with the boundaries.
44
We want to analyze a process, but we want to start with the boundaries first.
45
So we're going to go from receiving a work order to completing a work order.
46
That's the boundaries of our flowchart.
47
Now, I've got the team here because all of these activities, all of these tools are all team-based.
48
So imagine you're sitting down with your team
49
and the first thing you're going to do is brainstorm all of the steps in the process, right?
50
Talk to the experts.
51
How does the process work?
52
Use Post-it notes, right?
53
Don't try to do this in some software.
54
Use Post-it notes.
55
Write down all the activities.
56
And then once you're done brainstorming, organize those thoughts into that logical flow or that logical sequence of activities for your process.
57
Now that we have our process here, we're in that planning phase and we wanna create a target, right?
58
What sort of improvement are we gonna make?
59
And we wanna reduce defects by 25%.
60
Now, we can't make an improvement and we can't solve a problem without data.
61
And we know that most of our defects happen during final testing.
62
So now we need to collect a little bit of data and this is where the check sheet comes into play.
63
So the check sheet is a very simple tool for collecting, organizing and analyzing data.
64
Every problem you solve or every improvement you make should be based on data
65
and the check sheet is probably the most powerful tool for collecting data.
66
Now there's something wrong with the check sheet
67
that I'm showing you here on the screen and that problem is it doesn't have any metadata.
68
If you're collecting data and you want to make a high quality decision using that data, you also need metadata.
69
So when you're creating your check sheet, don't forget to include things like who and when and where.
70
All those key elements of data integrity and data accuracy are really important for making high quality decisions.
71
Okay, so we've got the team together.
72
And again, we did a little bit more brainstorming.
73
We said, okay, at final testing, we have eight defects that we want to collect some data on.
74
So we create this check sheet, we've got our metadata here, we hand this off to the team, and they come back to us a week later with a bunch of data.
75
Now this is fantastic.
76
We finally have some data that we can analyze.
77
And the question is, which defect do we focus on?
78
I want to improve our target.
79
So we originally said we want to reduce defects by 25%.
80
Well, now that we have a little bit of data, we can actually create a target.
81
So we have 145 defects across a whole week.
82
That's seven days.
83
That means we're averaging about 20 to 21 defects per day.
84
Now, if we can reduce that by 25%, we will eliminate five defects per day.
85
Now, we obviously can't focus on all these defects.
86
So the real question is, how do we know what to focus on?
87
And that's where the Pareto chart comes into play.
88
So the Pareto chart is another QC tool that allows you to analyze your data in search of the Pareto principle.
89
So what is the Pareto rule or what is this 80-20 rule?
90
So this is a natural phenomenon that was discovered by a guy named Vilfredo Pareto.
91
He's an Italian researcher who was studying land ownership and wealth distribution in Italy and in Europe.
92
And what he found is that 80% of the land was owned by 20% of the people.
93
And this 80-20 rule and this 80-20 phenomenon was also experienced by a guy named Joseph Duran.
94
Now, he gave credit for the tool to Vilfredo Pareto, but he was the one who popularized this idea of the 80-20 rule and this idea of the Pareto chart.
95
and what he told us and what he taught us is
96
that a Pareto chart helps you separate the vital few from the trivial many.
97
Now, what did Duran mean?
98
What he means is when you're solving a problem, there's often one or two key issues,
99
key root causes or key defects that you need to focus on to have a major impact on that particular situation.
100
And that's exactly what you see here.
101
When we take our data from the check sheet and we put it into this Pareto chart, we see that control PCB issues accounts for nearly 40% of our defects.
102
You can see if we come across here, we've got 40% of our defects coming directly from control PCB.
103
Now there's two things happening on this graph.
104
Obviously there's the blue bars, which are simply just the frequency or the count of defects that occurred throughout the week.
105
And then this black bar is actually the cumulative line.
106
So this first defect accounts for 40% and then we go up and up and up all the to 100%.
107
Now that we have this Pareto analysis, we know that control PCB is our primary issue.
108
It tells us what to focus on.
109
Now, we still don't understand why these issues are happening.
110
And this is where something like the cause and effect diagram can be incredibly useful.
111
So this is the fishbone diagram or the Ishikawa diagram.
112
There's all sorts of different names for it, but it is a cause and effect diagram.
113
And the way this works is we start with the effect that's over here on the right.
114
That's the head of the fish here in orange.
115
This is our effect.
116
And so step one of the cause and effect diagram is to start with a really well-written problem statement.
117
So I've put in PCB failures, but in reality, you want to have a much more descriptive problem statement than this.
118
And once you have this effect, you can start working through the fishbone process to analyze all of the potential causes and failures.
119
Now I'm showing here what's called the 8Ms.
120
And this is the beauty of the fishbone process is that it's a well-structured approach to root cause analysis.
121
It forces you to think about all of the potential different categories
122
or scenarios or causes that might be contributing to your problem.
123
Now, along with the cause and effect diagram are a number of tools that you should be using.
124
So I would recommend you get out your flow chart, look at your process, use your flow chart and ask yourself,
125
how might each step in the process fail and contribute to the effect that we're seeing.
126
Teamwork is also a must here.
127
You're not going to be a subject matter expert in all of those 8Ms
128
and you need people from operations and engineering and quality
129
and R&D and marketing
130
and maintenance to really do a thorough analysis in each of those areas to truly understand the root cause.
131
And then of course, brainstorming.
132
You're going to have to creatively think about and talk about
133
and discuss potential root causes that maybe you're not even aware of.
134
And then the five why analysis.
135
I love the five whys.
136
It really helps you go from a high level symptom down to the true root cause and really ask why, why, why to truly get to those, those real root causes that you need to address.
137
And then as you have that team discussion and you, you go through the process, you can identify potential root causes and contributing factors to the problem you're trying to solve.
138
Now, obviously, again, it's, we have to go back to that pretty principle.
139
We can't focus on everything.
140
We have to talk about the most likely root causes and the most likely contributing factors.
141
So again, at the end of your cause and effect diagram, you might identify three or four issues that you need to study further.
142
Now, I want to talk about this one, high humidity during assembly.
143
Now, as we were working through the cause and effect diagram process, the engineer who was helping us looked at our check sheet and noticed an interesting pattern.
144
What they noticed here, and I've highlighted here in yellow, is that Sunday, Monday, Tuesday, we only had a few defects, right?
145
Six and four and one.
146
Whereas on Wednesday, Thursday, Friday, you'll notice that our defect rate jumped up a little bit.
147
And what the engineer remembered is
148
that we had a rainstorm come through on Tuesday night and the humidity level in the facility really jumped up.
149
And so what the hypothesis here is that humidity is affecting our defect rate.
150
So I created this little table here to show the days of the week along with the defects and the humidity.
151
Now to truly understand this relationship, we have to create a scatter diagram.
152
So here's exactly what that scatter diagram looks like.
153
What we do here is we're plotting pairs of data.
154
So for example, on Sunday, we had six defects and 18% humidity.
155
You can see that right here.
156
That's this data point right here.
157
We had six defects, 18% humidity.
158
Now the way this scatter diagram works, or you might hear this called an XY scatter plot, is here on the x-axis, we put our controllable variable,
159
our independent variable, and then on the y-axis we put our response variable.
160
So here we believe that relative humidity is the independent variable that is affecting our response variable, which is defects.
161
And you can see here that there appears to be some relationship between PCB failures and humidity.
162
Now, it's really important when you're looking at a scatter diagram not to assume that this relationship is a causal relationship, right?
163
There's this really important concept that you can have correlation without causation.
164
Two parameters or two variables can correlate without having a cause and effect relationship.
165
So let's assume, though, let's assume that we've done a DOE here
166
and we've proven that humidity has an effect on our PCB defects.
167
We could come back to the scatter diagram.
168
We could say, OK, our target for PCB defects is five or less.
169
Let's call it five or less.
170
And so we come down here to humidity and say, okay, we want to control humidity to around 20% to keep our defects low.
171
Does that make sense?
172
And this is a great way, a scatter diagram is a great way to understand the relationship between two possible variables.
173
Now, once you've done your scatter diagram, you can quantify the relationship between those two variables.
174
So what I'm showing here is the Pearson correlation coefficient.
175
And this coefficient ranges from positive one all the way over
176
here on the left to negative 1 all the way over here on the right.
177
And that ranges from a perfectly positive correlation here.
178
You can see that as x changes, y changes identically.
179
And then same thing here with r equals minus 1.
180
This is a perfect negative correlation.
181
Now as we get closer to 0, we start to lose that relationship.
182
So an r value of 0 means there's no correlation between those two parameters.
183
As x changes, y basically does whatever it wants.
184
There's no relationship between those two variables.
185
Now, the next thing we could do in our analysis is to look at relative humidity over time.
186
So let's say we go out, we talk to our facilities engineers, we say, okay, give us the relative humidity within our environment, you know, every six hours for the last six months.
187
And we can take that data and we want to plot it because we need to understand
188
how relative humidity is changing within our facility.
189
And one of the ways you could analyze that data is with a histogram.
190
So a histogram is just a very simple bar chart that graphs the frequency of occurrence of continuous data.
191
And again, this is a great way to talk about your process.
192
Every process or every product
193
or every quality attribute out there has some level of random normal variation that will often occur in a pattern.
194
And as engineers, we need to understand what is the pattern associated with our outputs or our process.
195
And a histogram is a great way to understand the pattern or the variation in your process.
196
Now, you might grab this data and you might get like a skewed distribution or maybe a bimodal distribution or exponential distribution.
197
There's all sorts of distributions you might get, but it's great to know how your process is behaving.
198
Now, the other beautiful part about a histogram is you can take this data and let's overlay some some specification limits, right?
199
Now what we have is the beginnings of process capability.
200
So the histogram is a fantastic tool to quantify and understand how your process behaves.
201
And if you compare that against the specification limits, we can now start talking about process capability.
202
Okay, so we're on to the very last and final QC tool.
203
Let's assume we now control for humidity, and we want to make sure that that change has been effective over time.
204
A control chart is the right tool or the perfect tool to do that.
205
So what is a control chart?
206
It is essentially a tool that allows you to confirm that your process is in control.
207
Now, when I say in control, what I mean is that you're only experiencing normal variation.
208
When your process is experiencing normal cause variation, your data should fall within those control limits.
209
By the way, if you're new to SPC, I have a whole separate video on control charts.
210
You can go check it out.
211
I've got both the X bar our chart as well as attribute data.
212
And a control chart is a fantastic tool to use at the end of a project to monitor
213
and control your process and make sure that your changes were effective.
214
And let's take a look at what this looks like for our particular process.
215
So here's our process, right?
216
The first week of data, you can see we're really all over the place and our control limits are really wide because we're not controlling for humidity.
217
And we've got all this data and you can see on average, we have about eight defects per day, right?
218
And we're really jumping around here.
219
And then let's say on day nine, we start controlling for relative humidity.
220
And we've got our control chart and we're collecting data.
221
And you can see that for the next 20 plus days, our defect rate has dramatically fallen.
222
In fact, our new mean defects per day is around three.
223
So essentially, we've gone from eight defects per day down to three defects per day.
224
And we've hit our target of reducing defects by 25%.
225
We've gone from 20 plus defects a day down to about 15, all by controlling relative humidity in our process.
226
All right, that's it for today.
227
I hope you enjoyed it.
228
If you did, hit that like button.
229
Also, if you're serious about becoming a CQE, I've got a free course.
230
Go check it out.
231
It's at cqeacademy.com slash free course, where I cover the top 10 topics on the CQE exam.
232
And I also give you a bunch of great free practice exams to help you on that journey.
233
All right, I hope you enjoyed it.
234
Thanks so much.
235
I'll see you again.
236
Bye.

이 레슨에 대해

"The 7 Quality Control (QC) Tools Explained with an Example!"으로 쉐도잉 기법을 사용해 영어를 연습합니다.

매일 15~30분 꾸준히 연습하면 IELTS 스피킹에 대한 자신감이 길러집니다.

쉐도잉이란? 영어 실력을 빠르게 키우는 과학적 방법

쉐도잉(Shadowing)은 원래 전문 통역사 훈련을 위해 개발된 언어 학습 기법으로, 다언어 학자인 Dr. Alexander Arguelles에 의해 대중화된 방법입니다. 핵심 원리는 간단하지만 매우 강력합니다: 원어민의 영어를 들으면서 1~2초의 짧은 지연으로 즉시 소리 내어 따라 말하는 것——마치 '그림자(shadow)'처럼 화자를 따라가는 것입니다. 문법 공부나 수동적인 청취와 달리, 쉐도잉은 뇌와 입 근육이 동시에 실시간으로 영어를 처리하고 재현하도록 훈련합니다. 연구에 따르면 이 방법은 발음 정확도, 억양, 리듬, 연음, 청취력, 말하기 유창성을 크게 향상시킵니다. IELTS 스피킹 준비와 자연스러운 영어 소통을 원하는 분들에게 특히 효과적입니다.

섀도잉 방법: 단계별 전체 가이드 읽기 →