What is BIM coordination?
2
The definition of the word coordination is the organization of the different elements of a complex activity
3
so as to enable them to work together effectively.
4
The complex activity we are going to discuss here is the management of information related to buildings or infrastructure or BIM, building information modeling.
5
Information management or BIM coordination, when the information relates to buildings or infrastructure, is not a job title or a specific role.
6
Information management or BIM coordination is a function that everyone that is involved in the planning,
7
design, construction and operations of buildings or infrastructure has to participate in.
8
That is because every person and every discipline is involved with information.
9
You need information in order to do your job
10
and in doing your job you are probably producing or providing information that others will need to do the job.
11
If you are engaged in the planning, design, construction or operations of buildings or infrastructure, then you are involved in the communication or exchange of information,
12
which is the function of information management or BIM coordination.
13
So whether you are a client representative, architect, engineer, contractor, project manager, cost manager, design manager, procurement specialist,
14
safety manager, quality manager, environmental manager, facilities manager, specialist contractor, fabricator,
15
building product supplier, etc. You are involved in the function of information management
16
or BIM coordination since we are talking specifically about information management of buildings and infrastructure as opposed to general information management.
17
The confusion has arisen because some people believe incorrectly that BIM is only about the production of 3D models,
18
and therefore BIM coordination is just about coordinating those 3D models, or what is called clash detection.
19
But that is a very limited view of BIM and BIM coordination.
20
The international standard ISO 19650 has a far wider definition of BIM,
21
which includes all information that describe the physical and functional aspect of buildings and infrastructure.
22
This includes 3D models, geometric data,
23
alphanumeric data, and documentation, all managed in a common data environment CDE.
24
In that definition of BIM every person or discipline
25
that either needs information or who provides information has to engage with the management function of the CDE process.
26
Of course there are still hierarchies of management within the function
27
of information management from the client owner employer appointing party all the way through to the people who ultimately produce
28
or provide the information, the BIM authors.
29
There needs to be a information manager within each organization that is participating in a project, contributing to a specific task or discipline of work.
30
These are called task information managers.
31
They take responsibility for the information their own organization produces and approve it for sharing in the CDE.
32
Then there is a information manager who takes responsibility for a delivery team, a group of organizations in a specific phase or stage.
33
For example, this could be the lead designer for the design delivery team
34
or the main contractor for the construction delivery team or the facilities manager for the operations delivery team.
35
In each case, they are the lead appointed party responsible for the delivery of that phase
36
and they need an information manager who will liaise with the
37
other individual task information managers for the overall coordination of information for that phase or stage.
38
Of course, the client, owner, employer, appointing party also needs to have their own information manager
39
who will ultimately receive the information from the delivery team will need to check,
40
approve and accept that information so that it is authorized for use by others published in the CDE Common Data Environment.
41
This diagram describes the function of information management and the flow of information.
42
The requirements for information flow from the appointing party down in
43
the diagram through the hierarchy to the BIM authors who will produce the information.
44
The information flows back up the hierarchy in the CDE being checked and accepted at each stage.
45
Requirements also flow from right to left in the diagram.
46
In other words, the operations team should let the construction team know what they will need to perform the job,
47
and the construction team should let the design team know what they will need to perform the job.
48
The information flows from left to right to meet those requirements.
49
So you can see that information management is not the job or role of one person.
50
It is a function that is spread across all roles and disciplines who engage with the information.
51
Any project team
52
that thinks you only need to hire one BIM coordinator for
53
the project to manage everything has no idea how information management works.
54
Since the management of information relates specifically to buildings
55
and infrastructure involves the organization of the different elements of a complex activity so as to enable them to work together effectively.
56
This is by definition BIM coordination.
57
Thank you.

تنزيل التطبيق

كل ما تحتاجه للتحدث بطلاقة

تقييم النطق بالذكاء الاصطناعيتقييم كل جملة
تدريب IPAأتقن كل صوت
المفرداتابنِ رصيدك من الكلمات
لعبة المفرداتتعلّم أثناء اللعب
FOR YOU

فيديو موصى به

المفردات وملاحظات التحدث لهذا الدرس

هذا الدرس في المحادثة مبني على الفيديو “What is BIMCoordination?”. أكثر الكلمات تكرارًا في الفيديو: Bim, manager, management, coordination, infrastructure. يحتوي هذا الفيديو على 57 جملة و811 كلمة للتدرب على الترديد. مدة الكلام 5:17. يتكلم المتحدث بسرعة طبيعية، نحو 153 كلمة في الدقيقة، قريبة من المحادثة اليومية. 85% من الكلمات ضمن أكثر 3,000 كلمة شيوعًا في الإنجليزية، ويُستحسن مراجعة الباقي قبل البدء.

أهم المفردات في هذا الفيديو

15 كلمة من الفيديو تستحق التعلّم، مع النطق والمعنى:

الكلمةالنطقالمعنى
infrastructure اسم/ˈɪnfɹəˌstɹʌkt͡ʃə/بِنْيَة تَحْتِيَّة
discipline اسم/ˈdɪsəplɪn/اِنْضِبَاط, تَهْذِيب
requirement اسم/ɹɪˈkwaɪɹmənt/مَطْلَب, طَلَب
contractor اسم/ˈkɒnˌtɹæk.tə(ɹ)/مُقَاوِل
diagram اسم/ˈdaɪ.ə.ɡɹæm/مُخَطَط, رَسْم إِيضَاحِيّ
hierarchy اسم/ˈhaɪ.ə.ɹɑː(ɹ).ki/هَرَمِيَّة, سِلْسِلَةُ مَراتِب
element اسم/ˈɛləmənt/عُنْصُر
participate فعل/pɑːˈtɪs.ɪ.peɪt/شَارَكَ, سَاهَمَ
specialist اسم/ˈspɛʃəlɪst/مُتَخَصِّص, مُتَخَصِّصَة
employer اسم/ɪmˈplɔɪə/رَبّ عَمَل, رَبَّة عَمَل
approve فعل/əˈpɹuːv/صَدَّقَ, وَافَقَ
designer اسم/dɪˈzaɪnɚ/مُصَمِّم, مُصَمِّمَة
hire فعل/ˈhaɪɹ/أَجَّرَ
contribute فعل/kənˈtɹɪb.jut/سَاهَمَ
confusion اسم/kənˈfjuːʒən/اِلْتِبَاس

القواعد في هذا الفيديو

أكثر التراكيب التي يستخدمها المتحدث، مع العبارات نفسها من الفيديو:

التركيبفي الفيديو
المبني للمجهول be + اسم المفعول — التركيز على ما يحدث لا على من يفعلهis involved · are involved · is called
جمل الوصل who / which + جملة — معلومة إضافية عن شخص أو شيءeveryone that is · people who ultimately

نطق يحتاج إلى انتباه

  • أصوات “sh” و“zh”: coordination /kəʊˌɔːdɪˈneɪʃən/, specialist /ˈspɛʃəlɪst/, confusion /kənˈfjuːʒən/, detection /dɪˈtɛk.ʃən/, clash /ˈklæʃ/
  • الكلمات الطويلة — انتبه لموضع النبر: coordination /kəʊˌɔːdɪˈneɪʃən/, infrastructure /ˈɪnfɹəˌstɹʌkt͡ʃə/, hierarchy /ˈhaɪ.ə.ɹɑː(ɹ).ki/, participate /pɑːˈtɪs.ɪ.peɪt/, documentation /ˌdɑkjəmɛnˈteɪʃən/

أصوات يجدها متحدثو العربية صعبة:

  • /p/ — ليس /b/: انطقه مع نفخة هواء: discipline /ˈdɪsəplɪn/, appoint /əˈpɔɪnt/, participate /pɑːˈtɪs.ɪ.peɪt/, specialist /ˈspɛʃəlɪst/, employer /ɪmˈplɔɪə/
  • /v/ — ليس /f/: مع اهتزاز الأوتار الصوتية: approve /əˈpɹuːv/, involve /ɪnˈvɑlv/
  • تتابع الصوامت — لا تضف حركة بينها: infrastructure /ˈɪnfɹəˌstɹʌkt͡ʃə/, appoint /əˈpɔɪnt/, requirement /ɹɪˈkwaɪɹmənt/, contractor /ˈkɒnˌtɹæk.tə(ɹ)/, element /ˈɛləmənt/

كيف تتدرب بهذا الفيديو

  1. استمع إلى الفيديو كاملًا مرة واحدة دون أن تتكلم، ودوّن الكلمات التي لا تعرفها.
  2. ابدأ بسرعة 0.75×، وردّد جملة جملة، ثم عُد إلى السرعة العادية عندما يصبح الأمر سهلًا.
  3. سجّل صوتك وقارنه بالأصل، مع الانتباه إلى كلمات مثل infrastructure, discipline, requirement.

ما هي تقنية التظليل الصوتي؟

التظليل الصوتي (Shadowing) تقنية تعلم لغة مدعومة علمياً، طُورت أصلاً لتدريب المترجمين الفوريين المحترفين. الطريقة بسيطة لكنها قوية: تستمع لصوت إنجليزي أصلي وتكرره فوراً بصوت عالٍ — كظل يتبع المتحدث بتأخير 1-2 ثانية. تُظهر الأبحاث تحسناً كبيراً في دقة النطق والتنغيم والإيقاع وربط الأصوات والاستماع والطلاقة.

تقنية الشادوينغ: اقرأ الدليل الكامل خطوة بخطوة →