Hello guys, welcome to our YouTube channel.
2
In this video I'm gonna discuss about Fidic Yellow Book 2nd edition, which was published in 2017.
3
I hope you all know that this book consists of conditions of contract for plant and design build projects.
4
As a construction professional, it is really important to have a sound understanding on Fidic clauses.
5
When you say conditions, there are two types of conditions.
6
General conditions, and particular conditions.
7
First we'll discuss about general conditions.
8
Fidic Yellow Book 2017 consists of 21 clauses.
9
So I'm hoping to explain everything in this document in a series of videos.
10
So, make sure you subscribe to this channel
11
and hit the bell icon then you can join with me in the future videos as well.
12
Now let's start today's video with, clause number 1, general provisions.
13
This clause consists of 16 sub-clauses.
14
Let's discuss one by one.
15
Sub-clause 1.1, Definitions.
16
When you're referring to FIDIC documents, you must be very familiar with these defined words.
17
And be mindful that you must use these defined words in your documentation and correspondence, exactly the same way as they are written in this book.
18
For example, when you write accepted contract amount, it should be like this, and not like this.
19
Works should be like this, not like this.
20
This is really really important.
21
Ok, now let's go through these definitions.
22
There are 90 definitions altogether, so I'm not gonna describe one by one, and I will skip the straightforward ones.
23
I think it's better to start off with base date, since we will be discussing on advance payment certificate and guarantee under clause 14.
24
So, base date is the date 28 days prior to tender submission date.
25
But, there's a special word, latest, latest date of submission, which means if the tender submission date extended, then the base date automatically changes accordingly.
26
This base date is vital because the contractor shall do the pricing by considering the information, regulations and conditions prevailing at the base date.
27
Also, the rate analysis for the project is prepared with the cost data available at the time of base date.
28
So, the base date is generally used as a mechanism for the allocation of risk between employer
29
and contractor for changes that might occur during the period between the contractor pricing the tender and the signing of the contract.
30
So in general a base date is a reference date from which changes in conditions can be assessed.
31
To explain a little bit further, I'll link this to another definition, unforeseeable.
32
It says unforeseeable means not reasonably foreseeable by an experienced contractor by the base date.
33
So this base date is clearly connected with risks.
34
Okay, so now we'll move on to next definition, claim.
35
This is a very popular term I guess in the construction industry.
36
A claim can be defined as a request or an assertion, which means a confident statement with evidence from either party of the contract to the other for an entitlement
37
which of course is for an additional payment or an extension of time
38
if you are the contractor and if you are the employer a cost reduction may be.
39
Not only that, you can submit a claim for a relief as well.
40
I think this could be a relief from a delay damages or some kind of a penalty.
41
So, you can initiate a claim under various circumstances as described in this document, we will discuss about those under the relevant clauses.
42
For now, I want you to have a quick look at clause 20.2.4, fully detailed claim.
43
So you should be certain that you have fulfilled all these four requirements when you are submitting a claim.
44
Then I'm going to talk about compliance verification system.
45
However, under definitions, you cannot get a clear idea about it.
46
Therefore, I'll take you to sub-clause 4.9.2.
47
Basically this system is implemented to ensure that the contractor is maintaining the required quality during the construction, as well as all the functional requirements are fulfilled.
48
So if we go through the clause, it says, the contractor shall prepare and implement a compliance verification system to demonstrate that the design,
49
materials, employer-supplied materials, plant, work and workmanship comply in all respects with the contract.
50
Further, this system should be prepared referring to employers' requirements, specifications, and regulations.
51
So the contractor shall mention in this system how he's going to report the results of all inspections and tests carried out.
52
You must have heard the term, NCR, non-compliances report which are issued when the contractor fails to comply with the expected quality.
53
Also, in the event that any inspection or test identifies a non-compliance with the contract, sub-clause 7.5, defects and rejection shall apply.
54
So next, we'll talk about the definition, contract.
55
When you consider a construction contract, it doesn't mean only the contract agreement, there are a lot more to follow as shown here, letter of acceptance, letter of tender and addendums,
56
these conditions which means conditions of contract, employer's requirement, contractor's design and price proposals,
57
specifications, JV undertaking if it's applicable and other documents mentioned in contract agreement or LOA.
58
So, a construction contract is a very vast area.
59
Okay now let's talk about contract data.
60
Contract data is part A of particular conditions.
61
So it is actually some kind of link between general and particular conditions.
62
When you go through general conditions clauses, you will find a number of places, as stated in the contract data.
63
Which means certain sub clauses in the general conditions require that specific information.
64
So, you can find all the specific information relevant to the project under contract data, such as, employer's details, time for completion,
65
advance payment percentage, retention amount percentage, and so on.
66
Remember that contract data do not make any changes to the general conditions mentioned in FITIC.
67
If you want to change any of the sub clauses in general conditions, you shall do it using Particular Conditions Part B, Special Provisions.
68
We'll talk about those separately.
69
Next I'm gonna talk about, Contractors' Documents, which means the documents prepared by the contractor as described in Sub-Clause 5.2,
70
including calculations, digital files, computer programs and other software,
71
drawings, manuals, models, specifications, and other documents of a technical nature, and if we go to sub-clause 5.2,
72
it says contractors' documents shall comprise, as specified in the employer's requirements, required to satisfy all permits,
73
permissions, licenses and other regulatory approvals, which are the contractor's responsibility under sub-clause 1.13 compliance with laws,
74
and as described in sub-clause 5.6, as built records, and sub-clause 5.7, Operation and Maintenance Manuals.
75
So I want to show you something, in this document, most of the sub-clauses are connected to one or more sub-clauses.
76
So you need to be thorough with all these conditions when you are working with contract-related matters.
77
Then I will quickly talk about, Contractor's Equipment.
78
Make sure you always use the correct term equipment, not equipments.
79
Contractor's Equipment means all apparatus, equipment, machinery, construction plant, vehicles and other items required by the contractor for the execution of the works.
80
Here I want to highlight the words, execution, and works.
81
Works, clause number 1.1.89 means, permanent works and temporary works.
82
So equipment are used for the execution of temporary and permanent works.
83
But, anything that forms a part of permanent works, or anything that can be identified under temporary works, is not an equipment.
84
Equipment are only used for execution of works.
85
For example, if you have to supply a crane under the contract which you hand over to the client, then it's not a contractor's equipment.
86
Okay then we'll talk about, Contractor's Personnel.
87
Contractor's Personnel means the contractor's representative, who is the authorized person to be act on contractor's behalf,
88
and all personnel whom the contractor utilizes on site or other places, such as a fabrication yard, where the works are being carried out,
89
including the staff, labor and other employees of the contractor, and of each subcontractor, and any other personnel assisting the contractor in the execution of the works.
90
So, contractor's personnel includes all the subcontractor's personnel as well.
91
Then I will talk about, cost.
92
Cost means all expenditure including taxes, overheads, and similar charges excluding profit, reasonably incurred by the contractor in performing the contract.
93
So any expenditure before entering the contract cannot be taken as a cost.
94
So we talked about few definitions up to now.
95
I don't want to make this video too long since it might be boring
96
and I wanted to give a brief about this book from this video.
97
We'll talk about the remaining definitions and other clauses in the upcoming videos.
98
I would like to request all of you who are new
99
to the construction industry to have a look at Fidic Yellow Book because it will be very helpful to you.

المفردات وملاحظات التحدث لهذا الدرس

هذا الدرس في المحادثة بمستوى C1 مبني على الفيديو “FIDIC Yellow Book 2017 Explained”. أكثر الكلمات تكرارًا في الفيديو: clause, contract, conditions, contractor, date. يحتوي هذا الفيديو على 99 جملة و1470 كلمة للتدرب على الترديد. مدة الكلام 8:52. يتكلم المتحدث بسرعة طبيعية، نحو 166 كلمة في الدقيقة، قريبة من المحادثة اليومية. 82% من الكلمات ضمن أكثر 3,000 كلمة شيوعًا في الإنجليزية، ويُستحسن مراجعة الباقي قبل البدء.

أهم المفردات في هذا الفيديو

أصعب 15 كلمة في الفيديو، مع النطق والمعنى:

الكلمةالنطقالمعنى
clause اسم/klɔːz/جُمْلَة
contractor اسم/ˈkɒnˌtɹæk.tə(ɹ)/مُقَاوِل
expenditure اسم/ɛkˈspɛndɪt͡ʃə/صَرْف
fulfill فعل/fʊlˈfɪl/أَوْفَى, أَدَّى
reasonably ظرف/ˈɹiː.zən.ə.bli/بِشَكْل مَنْطِقِيّ
fabrication اسم/fæbɹɪˈkeɪʃən/تَصْنِيع
mindful صفة/ˈmaɪnd.fl̩/مُنْتَبِه
subcontractor اسممقاول
prevail فعل/pɹɪˈveɪl/يسود
circumstance اسم/ˈsɝ.kəmˌstæns/حَالَة, ظَرْف
defect اسم/ˈdiːfɛkt/خَلَل, عَيْب
allocation اسم/ˌæl.əˈkeɪ.ʃən/تَخْصِيص
calculation اسم/ˌkælkjuˈleɪʃn̩/حَسْب, مُحَاسَبَة
apparatus اسم/ˌæp.əˈɹeɪ.təs/أَدَاة, جِهَاز
retention اسم/ɹɪˈtɛnʃən/حِفْظ

الأفعال المركبة التي ستسمعها

الكلمةالنطقالمعنى
carry out فعل/ˈkæ.ɹi aʊt/شَغَّلَ, نَفَّذَ

جمل تستحق التكرار

جمل قصيرة وكاملة من الفيديو يمكنك استخدامها في الحديث اليومي:

  • First we'll discuss about general conditions.
  • Let's discuss one by one.
  • Then I'm going to talk about compliance verification system.
  • We'll talk about those separately.

القواعد في هذا الفيديو

أكثر التراكيب التي يستخدمها المتحدث، مع العبارات نفسها من الفيديو:

التركيبفي الفيديو
المبني للمجهول be + اسم المفعول — التركيز على ما يحدث لا على من يفعلهwas published · are written · is prepared
جمل الوصل who / which + جملة — معلومة إضافية عن شخص أو شيءedition, which was · submission, which means · assertion, which means

نطق يحتاج إلى انتباه

يستخدم المتحدث 19 من الصيغ المختصرة، مثل we'll, I'm, gonna. انطقها بصيغتها القصيرة كما تسمعها.

  • أصوات “th”: authorize /ˈɔθəɹaɪz/, thorough /ˈθʌɹoʊ/, altogether /ɔl.tuˈɡɛð.ɚ/
  • أصوات “sh” و“zh”: submission /səbˈmɪʃən/, verification /ˌvɛ.ɹə.fɪˈkeɪ.ʃən/, fabrication /fæbɹɪˈkeɪʃən/, workmanship /ˈwɜːk.mən.ʃɪp/, assertion /əˈsɜɹʃən/
  • الكلمات الطويلة — انتبه لموضع النبر: verification /ˌvɛ.ɹə.fɪˈkeɪ.ʃən/, expenditure /ɛkˈspɛndɪt͡ʃə/, reasonably /ˈɹiː.zən.ə.bli/, fabrication /fæbɹɪˈkeɪʃən/, foreseeable /fɔɹˈsi.ə.bəl/

أصوات يجدها متحدثو العربية صعبة:

  • /p/ — ليس /b/: انطقه مع نفخة هواء: expenditure /ɛkˈspɛndɪt͡ʃə/, comply /kəmˈplaɪ/, workmanship /ˈwɜːk.mən.ʃɪp/, prevail /pɹɪˈveɪl/, comprise /kəmˈpɹaɪz/
  • /v/ — ليس /f/: مع اهتزاز الأوتار الصوتية: verification /ˌvɛ.ɹə.fɪˈkeɪ.ʃən/, prevail /pɹɪˈveɪl/, overhead /ˈəʊvəˌhɛd/
  • تتابع الصوامت — لا تضف حركة بينها: clause /klɔːz/, contractor /ˈkɒnˌtɹæk.tə(ɹ)/, consist /kənˈsɪst/, expenditure /ɛkˈspɛndɪt͡ʃə/, comply /kəmˈplaɪ/

كيف تتدرب بهذا الفيديو

  1. استمع إلى الفيديو كاملًا مرة واحدة دون أن تتكلم، ودوّن الكلمات التي لا تعرفها.
  2. ابدأ بسرعة 0.75×، وردّد جملة جملة، ثم عُد إلى السرعة العادية عندما يصبح الأمر سهلًا.
  3. سجّل صوتك وقارنه بالأصل، مع الانتباه إلى كلمات مثل clause, contractor, expenditure.

ما هي تقنية التظليل الصوتي؟

التظليل الصوتي (Shadowing) تقنية تعلم لغة مدعومة علمياً، طُورت أصلاً لتدريب المترجمين الفوريين المحترفين. الطريقة بسيطة لكنها قوية: تستمع لصوت إنجليزي أصلي وتكرره فوراً بصوت عالٍ — كظل يتبع المتحدث بتأخير 1-2 ثانية. تُظهر الأبحاث تحسناً كبيراً في دقة النطق والتنغيم والإيقاع وربط الأصوات والاستماع والطلاقة.

تقنية الشادوينغ: اقرأ الدليل الكامل خطوة بخطوة →