1
In this video we will explain how to assign calendar in each activity.
2
To do that you will click on excavation activity for example
3
and you go under general activity calendar
4
and you choose from display you have the global project calendars
5
and we created one project calendar right now so you click on project calendar you will have project A for contractor work.
6
The excavation activity is undertaken by the contractor
7
so contractor calendar will be assigned for this activity
8
and you click the plus sign here to do
9
that for the compaction again you will assign for contractor
10
so what about if you have more activities here it is very time-consuming to go over each activity
11
and review which calendar was assigned here so you can right-click columns
12
and you search from the available option calendar
13
and double click it will be shown here okay
14
so this is all the calendars here and what about other two activities here they also will be executed by the contractor.
15
So instead of doing this one by one, you can use the fill down option.
16
You can click on this activity and I want to match it to the completion of foundation.
17
So this activity first, you click on the calendar, then control on the keyboard,
18
then completion of foundation right click fill down then it will be assigned to the contractor
19
if you wanna do this quickly you have to select first the activity
20
which has your desired calendar then go to the destination activity
21
so let's do that for the start of foundation I wanna also have it project a contractor calendar
22
so you click on any activity which has the project a contractor calendar then
23
and also you have to click on the calendar column here not here
24
or here the contractor calendar so the calendar column
25
because you want to fill down the calendar column control on
26
the keyboard click on the start of foundation right click then
27
fill down i have only one calendar assigned here in the project
28
but what about the engineering work maybe I will have one activity.
29
It's called Submitter Review
30
and approval by the consultant consultant maybe will work only five days per week not six days per week
31
so the contractor has a calendar
32
if you remember the project a calendar project a contractor calendar had six days working days
33
but for the consultant it has only five days so you create a new calendar
34
You assign it to the engineers activities or the consultant activities so you can go to enterprise calendar
35
I will also add a new calendar
36
and I you don't want to do the same for a new global calendar
37
so I will have the same contractor calendar again and I will rename it project a consultant
38
and I will go to modify
39
and maybe they are off the consultant is off on site
40
for Friday on Saturday I will go to total work hours per day then work week
41
so Saturday will be zero so it will automatically be here
42
so for the consultant he will not be working on Friday
43
and saturdays then click ok
44
when we have the duration here it will reflect only the working days
45
so if i assign the new calendar i have just created into any activity it will skip any friday
46
and saturday they will not count that
47
so it will reflect on dates as well in significant way
48
so this is how you assign calendars
49
and use the fill down option fill down also is not
50
exclusive for calendar assignments you can do it for duration as well
51
so for excavation it has for example eight days
52
so you want to compaction eight days as well this is only an example
53
but you can apply it into huge set of data in
54
the schedule you click on the original duration column control compaction
55
this is my destination i want to show eight days here as well right click
56
and fill down so it became eight days as well
57
so i will revert this back into six days and
58
if you remember also i showed this before as 10 days
59
but now it's eight days the reason for that is
60
because i assigned a new calendar to match the overall dates
61
so the original duration was reduced also to eight days
62
so make sure
63
that you assign calendars properly first then you adjust the original
64
duration later on in the next lesson we will talk about columns and time scale

下载应用

流利口语所需的一切

AI 发音评分逐句打分
音标练习掌握每个音
词汇学习建立你的词库
词汇游戏边玩边学

同频道

FOR YOU

推荐视频

本课的词汇与口语要点

这节 C1 级别的口语课以视频“11. Assign Calendars and Fill Down in Primavera P6”为素材。 视频中反复出现的词有:calendar, click, activity, contractor, project。 这段视频共有 64 个句子、763 个单词可供跟读。 讲话部分时长为 5:30。 说话人语速平稳,每分钟约 139 个词,很适合跟读。 83% 的单词属于英语最常用的 3,000 词,其余的词建议在练习前先学一下。

视频中的重点词汇

视频中最难的 8 个单词,附发音和释义:

单词发音释义
assign 动词/əˈsaɪn/分配, 分派
compaction 名词/kəmˈpækʃən/壓實 /压实
rename 动词/ɹiːˈneɪm/重命名, 重新命名
undertake 动词/ˌʌndəˈteɪk/進行 /进行
modify 动词/ˈmɑ.dɪˌfaɪ/修改
consume 动词/kənˈsum/耗費 /耗费, 消耗
execute 动词/ˈɛksɪˌkjuːt/處決 /处决, 處死 /处死
adjust 动词/əˈd͡ʒʌst/調整 /调整

需要注意的发音

说话人用了 3 次缩略和弱读形式,例如 wanna, don't。请按听到的简短形式来说。

  • “sh” 和 “zh” 音: compaction /kəmˈpækʃən/, excavation /ˌɛkskəˈveɪʃn/

中文母语者容易读错的音:

  • /v/ — 不要读成 /w/,上齿轻触下唇: excavation /ˌɛkskəˈveɪʃn/, revert /ɹɪˈvɝt/
  • 词尾辅音 — 要读清楚,后面不要加元音: columns /ˈkɑləmz/, revert /ɹɪˈvɝt/, undertake /ˌʌndəˈteɪk/, execute /ˈɛksɪˌkjuːt/, adjust /əˈd͡ʒʌst/
  • /æ/ — 嘴张大,不要读成 /e/: contractor /ˈkɒnˌtɹæk.tə(ɹ)/, compaction /kəmˈpækʃən/

如何用这段视频练习

  1. 先完整听一遍视频,不要开口,记下不认识的单词。
  2. 用正常速度逐句跟读,每句重复到你的节奏与说话人一致为止。
  3. 录下自己的声音并与原声对比,特别注意 assign, compaction, rename 这类单词。

什么是跟读法?

跟读法 (Shadowing) 是一种有科学依据的语言学习技巧,最初开发用于专业口译员的培训,并由多语言者Alexander Arguelles博士普及。这个方法简单而强大:您在听英语母语原声的同时立即大声重复——就像是一个延迟1-2秒紧跟说话者的影子。与被动听力或语法练习不同,跟读法强迫您的大脑和口腔肌肉同时处理并模仿真实的讲话模式。研究表明它能显着提高发音准确性,语调,节奏,连读,听力理解和口语流利度——使其成为雅思口语备考和真实英语交流最有效的方法之一。

影子跟读法: 阅读完整分步指南 →