calendars are very important because it helps identify the working days
2
and working hours which will reflect on the schedule dates schedule nature
3
so for example for this activity compaction I have a planned start date 9th of August
4
and it will take 7 days to complete so
5
if you sum this together like seven days after 9th of august it will give you 16th
6
but the finish here is 17th of august the reason is
7
there is maybe one non-working day like one day weekend
8
or something like that so
9
if you apply this to the whole schedule it will affect
10
the outcome of the schedule the total float the planned finish date the the whole behavior of the network
11
to create or manage calendars you go to enterprise calendars
12
and you have here the global
13
and they are pre-identified calendars i maybe i used to work on projects
14
which have some of these calendars some of these calendars also will be added by default into promovera p6
15
and some of them i have used before
16
so this is will fall under global for the resources calendar I can create calendars for the resources only.
17
For example, the Carpenters, I outsource them.
18
They will work only two or three days per week.
19
So I have calendar only for the resource of carpenters
20
but they are not commonly used because otherwise it will interfere with other schedule logic
21
and duration so no one actually does it so
22
if I want to add a new calendar into my project
23
so I have to create calendars here in the project then I go back to the activities
24
and choose which active which calendar applies here
25
and assign it i click add and i want to choose one from the global
26
so let's take the current contractor's calendar okay so this is for my project project a contractor
27
let's say if we can modify it
28
so i have here for the i have here total work the hour total work hours per day
29
and detailed work hours per day for the total work hours per day
30
so i have here friday off it is my weekend so
31
if you go to in friday you will find work hours
32
day is zero for other activities i specified eight days working hours
33
so if you want to make it 10 days in your project for example you cannot go over each activity
34
or each day and make it 10 days you go here for the work week
35
and make 10 days for each activity so let's say i will have it 10 days
36
and for time periods you also make it 10 days and
37
if you are working 60 days per week and one day only weekend
38
so it means it is 60 days also the same hours per month so it depends on your project
39
you know so you can have the math for for the month
40
and the year as well let's say
41
that for maybe special occasion i am working half day only on this wednesday
42
so i can assign only five working hours per day okay
43
so this is for the total work hours per day overall
44
but let's go over day by day so if we go detailed
45
and also by the way so for total hour per day
46
if if i wanna have this maybe public holiday for example on 17th
47
so i i double click on it
48
or i another option is i click on it
49
and make it um none work so for detailed work hours per day so for each day
50
you can specify for example how many hours so the white here are the work working hours
51
the white cells and let's say
52
that i wanna this is seven this is five o'clock
53
so this is four o'clock 4 30 it divides here into half an hour
54
so this is 16 hour 16 which is 4 p.m
55
so this is 4 p.m 4 30 5 5 30 so let's say i i work also 5 to 5 30
56
and 5 30 to 6 o'clock so i wanna work this as well
57
if you wanna choose maybe there is one hour break for example
58
so you double click from one to two o'clock for example
59
so this is how this is a of calendars
60
so this is something high level so after all these exchanges
61
and especially the holidays
62
when you assign the calendar back to the activity it will affect the duration here
63
and the start and finish because the original duration it's a seven
64
so by default it's a seven working days
65
so what Pramavera does is we will take into account the seven days after
66
that they will go check the activity calendar here
67
and they will calculate seven working days so for example
68
if it starts 14th so they will make the start date 14th
69
and calculate and or count seven days afterwards
70
so one two three they will skip that four five skip friday six seven
71
so it will be completed on 22nd of august
72
so that's why promovera calendar is very important
73
and they have you have to manage it correctly so in the next lecture we will assign the calendar into activity

下载应用

流利口语所需的一切

AI 发音评分逐句打分
音标练习掌握每个音
词汇学习建立你的词库
词汇游戏边玩边学

同频道

FOR YOU

推荐视频

本课的词汇与口语要点

这节 C1 级别的口语课以视频“10. Create and Manage Calendars in Primavera P6”为素材。 视频中反复出现的词有:calendar, hour, seven, example, project。 这段视频共有 73 个句子、862 个单词可供跟读。 讲话部分时长为 5:56。 说话人语速平稳,每分钟约 145 个词,很适合跟读。 87% 的单词属于英语最常用的 3,000 词,其余的词建议在练习前先学一下。

视频中的重点词汇

视频中最难的 15 个单词,附发音和释义:

单词发音释义
calendar 名词/ˈkæl.ən.də/日曆 /日历, 曆 /历
assign 动词/əˈsaɪn/分配, 分派
resource 名词/ɹɪˈzɔːs/資源 /资源
duration 名词/dʒʊˈɹeɪ.ʃən/時間 /时间, 長短 /长短
default 名词/dɪˈfɔlt/違約 /违约, 暴雷
skip 动词/skɪp/跳
calculate 动词/ˈkælkjʊleɪt/計算 /计算, 算
carpenter 名词/ˈkɑɹpəntɚ/木匠
afterwards 副词/ˈæf.tɚ.wɚdz/然後 /然后
reflect 动词/ɹɪˈflɛkt/反映, 反射
commonly 副词/ˈkɑmənli/通常
enterprise 名词/ˈɛntəˌpɹaɪz/企業 /企业
occasion 名词/əˈkeɪ̯ʒən/場合 /场合, 機會 /机会
depend 动词/dɪˈpɛnd/信任, 信賴 /信赖
mathematics 名词/mæθ(.ə)ˈmæt.ɪks/數學 /数学, 算學 /算学

视频中的语法

说话人最常用的结构,并附上视频中的原话:

结构视频中的用法
条件句 if + 从句,will/would + 动词 — 条件及其结果if it starts 14th so they will make
被动语态 be + 过去分词 — 强调发生了什么,而不是谁做的will be added · will be completed

需要注意的发音

说话人用了 4 次缩略和弱读形式,例如 wanna。请按听到的简短形式来说。

  • “sh” 和 “zh” 音: duration /dʒʊˈɹeɪ.ʃən/, occasion /əˈkeɪ̯ʒən/, compaction /kəmˈpækʃən/

中文母语者容易读错的音:

  • 词尾辅音 — 要读清楚,后面不要加元音: resource /ɹɪˈzɔːs/, default /dɪˈfɔlt/, skip /skɪp/, calculate /ˈkælkjʊleɪt/, afterwards /ˈæf.tɚ.wɚdz/
  • /r/ 和 /l/ 的区别: reflect /ɹɪˈflɛkt/, correctly /kəˈɹɛk(t).li/
  • /æ/ — 嘴张大,不要读成 /e/: calendar /ˈkæl.ən.də/, calculate /ˈkælkjʊleɪt/, afterwards /ˈæf.tɚ.wɚdz/, mathematics /mæθ(.ə)ˈmæt.ɪks/, contractor /ˈkɒnˌtɹæk.tə(ɹ)/

如何用这段视频练习

  1. 先完整听一遍视频,不要开口,记下不认识的单词。
  2. 用正常速度逐句跟读,每句重复到你的节奏与说话人一致为止。
  3. 录下自己的声音并与原声对比,特别注意 calendar, assign, resource 这类单词。

什么是跟读法?

跟读法 (Shadowing) 是一种有科学依据的语言学习技巧,最初开发用于专业口译员的培训,并由多语言者Alexander Arguelles博士普及。这个方法简单而强大:您在听英语母语原声的同时立即大声重复——就像是一个延迟1-2秒紧跟说话者的影子。与被动听力或语法练习不同,跟读法强迫您的大脑和口腔肌肉同时处理并模仿真实的讲话模式。研究表明它能显着提高发音准确性,语调,节奏,连读,听力理解和口语流利度——使其成为雅思口语备考和真实英语交流最有效的方法之一。

影子跟读法: 阅读完整分步指南 →