1
calendars are very important because it helps identify the working days
2
and working hours which will reflect on the schedule dates schedule nature
3
so for example for this activity compaction I have a planned start date 9th of August
4
and it will take 7 days to complete so
5
if you sum this together like seven days after 9th of august it will give you 16th
6
but the finish here is 17th of august the reason is
7
there is maybe one non-working day like one day weekend
8
or something like that so
9
if you apply this to the whole schedule it will affect
10
the outcome of the schedule the total float the planned finish date the the whole behavior of the network
11
to create or manage calendars you go to enterprise calendars
12
and you have here the global
13
and they are pre-identified calendars i maybe i used to work on projects
14
which have some of these calendars some of these calendars also will be added by default into promovera p6
15
and some of them i have used before
16
so this is will fall under global for the resources calendar I can create calendars for the resources only.
17
For example, the Carpenters, I outsource them.
18
They will work only two or three days per week.
19
So I have calendar only for the resource of carpenters
20
but they are not commonly used because otherwise it will interfere with other schedule logic
21
and duration so no one actually does it so
22
if I want to add a new calendar into my project
23
so I have to create calendars here in the project then I go back to the activities
24
and choose which active which calendar applies here
25
and assign it i click add and i want to choose one from the global
26
so let's take the current contractor's calendar okay so this is for my project project a contractor
27
let's say if we can modify it
28
so i have here for the i have here total work the hour total work hours per day
29
and detailed work hours per day for the total work hours per day
30
so i have here friday off it is my weekend so
31
if you go to in friday you will find work hours
32
day is zero for other activities i specified eight days working hours
33
so if you want to make it 10 days in your project for example you cannot go over each activity
34
or each day and make it 10 days you go here for the work week
35
and make 10 days for each activity so let's say i will have it 10 days
36
and for time periods you also make it 10 days and
37
if you are working 60 days per week and one day only weekend
38
so it means it is 60 days also the same hours per month so it depends on your project
39
you know so you can have the math for for the month
40
and the year as well let's say
41
that for maybe special occasion i am working half day only on this wednesday
42
so i can assign only five working hours per day okay
43
so this is for the total work hours per day overall
44
but let's go over day by day so if we go detailed
45
and also by the way so for total hour per day
46
if if i wanna have this maybe public holiday for example on 17th
47
so i i double click on it
48
or i another option is i click on it
49
and make it um none work so for detailed work hours per day so for each day
50
you can specify for example how many hours so the white here are the work working hours
51
the white cells and let's say
52
that i wanna this is seven this is five o'clock
53
so this is four o'clock 4 30 it divides here into half an hour
54
so this is 16 hour 16 which is 4 p.m
55
so this is 4 p.m 4 30 5 5 30 so let's say i i work also 5 to 5 30
56
and 5 30 to 6 o'clock so i wanna work this as well
57
if you wanna choose maybe there is one hour break for example
58
so you double click from one to two o'clock for example
59
so this is how this is a of calendars
60
so this is something high level so after all these exchanges
61
and especially the holidays
62
when you assign the calendar back to the activity it will affect the duration here
63
and the start and finish because the original duration it's a seven
64
so by default it's a seven working days
65
so what Pramavera does is we will take into account the seven days after
66
that they will go check the activity calendar here
67
and they will calculate seven working days so for example
68
if it starts 14th so they will make the start date 14th
69
and calculate and or count seven days afterwards
70
so one two three they will skip that four five skip friday six seven
71
so it will be completed on 22nd of august
72
so that's why promovera calendar is very important
73
and they have you have to manage it correctly so in the next lecture we will assign the calendar into activity

アプリをダウンロード

流暢に話すために必要なすべて

AI発音採点文ごとに採点
IPA練習すべての音をマスター
単語学習自分の単語帳を作る
単語ゲーム遊びながら覚える

同じチャンネル

FOR YOU

おすすめ動画

このレッスンの語彙とスピーキングのポイント

このC1レベルのスピーキングレッスンは、動画「10. Create and Manage Calendars in Primavera P6」を教材にしています。 繰り返し出てくる語は次のとおりです:calendar, hour, seven, example, project。 この動画には、シャドーイング用の文が73文、単語が862語あります。 音声の長さは5:56です。 話す速さは1分あたり約145語で安定しており、シャドーイングしやすいペースです。 単語の87%は英語の頻出3,000語に含まれます。残りは練習の前に確認しておきましょう。

この動画の重要語彙

動画の中で特に難しい単語15語を、発音と意味つきで紹介します。

単語発音意味
calendar 名詞/ˈkæl.ən.də/暦, カレンダー
assign 動詞/əˈsaɪn/割り当てる
resource 名詞/ɹɪˈzɔːs/資源, 資産
duration 名詞/dʒʊˈɹeɪ.ʃən/期間, 存続
default 名詞/dɪˈfɔlt/デフォルト
skip 動詞/skɪp/はね回る
calculate 動詞/ˈkælkjʊleɪt/計算する
carpenter 名詞/ˈkɑɹpəntɚ/大工
afterwards 副詞/ˈæf.tɚ.wɚdz/その後, それから
reflect 動詞/ɹɪˈflɛkt/跳ね返す, 反射する
enterprise 名詞/ˈɛntəˌpɹaɪz/企業, 事業
occasion 名詞/əˈkeɪ̯ʒən/場合, 機会
depend 動詞/dɪˈpɛnd/依存する
mathematics 名詞/mæθ(.ə)ˈmæt.ɪks/数学
lecture 名詞/ˈlɛk.t͡ʃə/講義

この動画の文法

話し手がよく使っている文型を、動画の実際の表現とともに紹介します。

文型動画での表現
条件文 if + 節, will/would + 動詞 — 条件とその結果if it starts 14th so they will make
受動態 be + 過去分詞 — 誰がするかより、何が起きるかに焦点を当てるwill be added · will be completed

注意したい発音

話し手はwannaなど、短縮形や弱形を4回使っています。聞こえたとおりの短い形で発音しましょう。

  • 「sh」と「zh」の音: duration /dʒʊˈɹeɪ.ʃən/, occasion /əˈkeɪ̯ʒən/, compaction /kəmˈpækʃən/

日本語話者が苦手な音:

  • /r/ と /l/ の区別 — /l/ は舌先を歯茎につけ、/r/ はどこにもつけない: reflect /ɹɪˈflɛkt/, correctly /kəˈɹɛk(t).li/
  • /f/ — 「フ」ではなく、上の歯と下唇で出す: default /dɪˈfɔlt/, specify /ˈspɛs.əˌfaɪ/, afterwards /ˈæf.tɚ.wɚdz/, reflect /ɹɪˈflɛkt/, float /fləʊt/
  • 子音の連続 — 間に母音を入れない: default /dɪˈfɔlt/, skip /skɪp/, calculate /ˈkælkjʊleɪt/, specify /ˈspɛs.əˌfaɪ/, afterwards /ˈæf.tɚ.wɚdz/

この動画での練習方法

  1. まず声を出さずに動画を最後まで聞き、知らない単語をメモします。
  2. 通常の速度で一文ずつシャドーイングし、話し手のリズムに合うまで繰り返します。
  3. 自分の声を録音して元の音声と比べます。calendar, assign, resourceなどの単語に特に注意しましょう。

シャドーイングとは?英語上達に効果的な理由

シャドーイング(Shadowing)は、もともとプロの通訳者養成プログラムで開発された言語学習法で、多言語習得者として知られるDr. Alexander Arguelles によって広く普及されました。方法はシンプルですが非常に効果的:ネイティブスピーカーの英語を聞きながら、1〜2秒の遅延で声に出してすぐに繰り返す——まるで「影(shadow)」のように話者を追いかけます。文法ドリルや受動的なリスニングと異なり、シャドーイングは脳と口の筋肉が同時にリアルタイムで英語を処理・再現することを強制します。研究により、発音精度、抑揚、リズム、連音、リスニング力、そして会話の流暢さが大幅に向上することが確認されています。IELTSスピーキング対策や自然な英語コミュニケーションを目指す方に特におすすめです。

シャドーイングのやり方: ステップ別の完全ガイドを読む →