Are you wondering what needs to be included in project management status reports?
2
Well, in this video, I'm going to share with you what exactly you should have in your project status report.
3
And if you're in need of help to build your project management skills, I have an amazing free training for you, and I'm going to put the link for you under this video.
4
Hi, if you're new here, welcome.
5
My name is Adriana Girdler, and on this channel, you're going to get the best career and project management advice.
6
please consider subscribing as it really helps us grow this awesome community.
7
Now, if you're ready to learn more about project status updates, then let's get to it.
8
What is a project status report?
9
Well, it basically summarizes what your project progress is in comparison to project plan.
10
Now there's many ways you can do this.
11
You can put your project status report in a Word document.
12
You can put it in a PowerPoint.
13
You can create a page on a web-based platform if you actually use something like that for your project.
14
There are different ways that you can put your status report.
15
Now, who would you send this to?
16
Well, you would send it to all the stakeholders of the project.
17
And again, don't forget who stakeholders are.
18
They're anyone who touches the project.
19
It could be people like your team members who are very in-depth and understand what's going on.
20
It could be steering committee members, sponsors.
21
It could also be senior executives who are on the peripheral edge of communication when it comes to your project.
22
It could also be the end user or department who is receiving the deliverable.
23
Again, anyone who touches a project really should have an understanding of your status update report.
24
You want to use it as a communication tool.
25
It really is to keep everyone in the loop.
26
Now, what's the frequency that you do with this status update report?
27
I personally like once a month.
28
I think that's really helpful.
29
You have enough things that have gone by and occurred so that when you have your status update report.
30
It actually has some good information and it will be different than your last status update report.
31
So that frequency is really important.
32
Now, how would you distribute this?
33
It really is dependent upon the type of document platform that you use.
34
So if you're doing more of a Word document or PowerPoint, you may want to email that out to people and make that just a monthly reoccurrence.
35
You may have a project share drive that maybe you want to put it on there and people go to it, or like I said, you may want to use a web-based platform.
36
I use Microsoft Office SharePoint and I actually create all my project documents on there and I bring people to it.
37
So there's definitely different ways depending on really how do you use and communicate with your projects.
38
Now, what I'm going to show you next is what actually goes into that status update report.
39
Project summary.
40
This is the first thing that you need to do.
41
So let me show you an example.
42
Follow me.
43
So with here we have the title of our update
44
and it's a monthly update and here's the date of it being updated, which was the second.
45
And your first section always in any update is a project summary.
46
Now there's really good reason for this.
47
It's because you want to include information to remind people, all those stakeholders, what it is that we're doing and what is it that you would include in this project summary.
48
Well, the scope statement, which is what is it that I'm responsible for from a delivery standpoint and for this particular project,
49
we're implementing a new future state security center.
50
And it's very specific with focus on streamlining people activities and implementing some technology to support new ways of working.
51
Now we also include the project priority matrix because this is going to let people know what your constraints are, what you're willing to optimize and accept from a scope,
52
time, and budget perspective.
53
This becomes really handy when you have people off to the side asking you to, oh, just add this element without having an understanding of everything else.
54
So you can bring them back to this and saying, hey, I can't do it biggest constraint is time and what you're asking me to do is to increase time.
55
Unless you have money, which is budget, in order to help me out, I'm not able to do it.
56
So it becomes a real powerful tool for you
57
and in fact in my Slay Project Management course with the link under this video, I actually go into this in great detail.
58
I love this Project Priority Matrix.
59
And now the next thing that you would have in your project summary is your high level milestones, not your detail, just very high level.
60
You want to give an overarching view to anybody who's looking at this.
61
What is it that we're doing and when are we delivering it by?
62
It's really very high level.
63
It supports a scope statement in the priority matrix so that anyone coming into it, especially a brand new person,
64
can get very quickly what is your project all about so
65
when they read the rest of the information in your status update, it makes sense.
66
Overall project status.
67
This is very simply put, what is the overall status of your project?
68
Are you on track or at risk?
69
go back to that example
70
so I can show you more okay now we want to go to the overall oops project status
71
which is basically saying overall my project as a whole how
72
is it is it on track do I have some issues
73
I like to use a stoplight system of green yellow
74
and red and green just means you're on track yellow I may have some potential risks
75
but we're working on it in red is I definitely have
76
some issues I'm probably going to need some intervention in order to ensure
77
that I get out of that not a bad thing to have any reds
78
or yellows in fact I always tell everyone you need to have reds and yellows
79
if I come across a project that's always in green status I question it in saying I don't know
80
if they actually know what's going on because I've never come across a project
81
that is constantly 100% in green status on track unless it's just myself and I have complete 100% control.
82
So if someone were to just look at the project summary and they just want to say, hey, how's this project?
83
Right away, immediately they know this project overall is on track.
84
Project deliverables or major milestone status.
85
This is the heartbeat of your status report.
86
So this is where all the detail is going to be.
87
Now that we have the project summary, which is really important, we have our overall status, which I'm saying is green.
88
Now we're going to get to the heart of this project status update, and that is project deliverable status.
89
So again, using the same stoplight system of green,
90
yellow, and red, I'm now going to be very specific to what deliverables I'm going to be giving a status on.
91
Now what I usually do is in my charter, I know what my major deliverables are and I'm just going to use those same deliverables in my monthly status update.
92
So this is not an exhaustive list.
93
This is just an example I'm giving you in regards to this was an actual real project and due to confidentiality, I can't necessarily put everything in there, but just to give you an idea of some things.
94
So from a deliverable standpoint of this project, we had upgrade of computer hardware, upgrade furniture we had to look at hiring new resources
95
and we had to do some training believe you me there's a lot more
96
but for this example I just want to make it short
97
and sweet for you now it's really important
98
because this is the heartbeat of everything this is reading getting the nitty-gritty is define what your deliverable is
99
because I promise you people come in with assumptions
100
and you want to negate those assumptions by just defining it
101
and then you want to give your status for each one
102
green yellow red green again do not be afraid of having reds
103
and yellows it just means that you understand your project you're on top of everything
104
and don't forget here yellow potential risk but the team is monitoring them
105
and if I have a red it means my team is working on fixing the issue
106
that could be literally them going in
107
and doing themselves me reaching out to maybe some steering committee members whatever it may be
108
and And your comment is for each deliverable.
109
So for example, the upgrading of the computer hardware.
110
As of this update, everything's on track.
111
Items have been ordered.
112
Great.
113
Updating, upgrading our furniture.
114
Well, we're having some issues because the original design configuration, we can't seem to get what we originally thought we designed and we're ordering.
115
So we're trying to find alternatives with our supplier.
116
That to me is a yellow.
117
We're monitoring it.
118
We're coming up with an alternative solution.
119
It's not a red because it's not an issue.
120
It just means we have to find a different solution for it
121
Resources I marked down as a red
122
because we're having a difficult time finding qualified resources We're going to revisit our requirements
123
and definitely go to our steering committee to get approval for those changes
124
And then I got some training execution which if I were to scroll here is really towards the end of my
125
Project and I'm not there yet.
126
I just said as of August 2nd deliverable hasn't started yet
127
So I'm giving myself a little bit of a bonus by saying it's green.
128
It's on track because it is on track I'm doing everything else in order to make it work.
129
So this is your heartbeat Again, you want to have your project summary so that people understand it
130
and Even though my project deliverable has some reds
131
and yellows I still feel as a project manager my project is green even though I have a few yellows
132
and reds because I have plans in place in order to address them Issues and risk.
133
This is where you're going to outline some high level external elements
134
that are impacting your project that you want to share with your stakeholders.
135
Anything that's going to impact scope, time, or budget.
136
Let's go back to that example.
137
Now we're going to go to the last section of your status update, issues and risks.
138
So this is where you're going to highlight any issues
139
that are not connected to a deliverable because there are things like
140
that and you just want to give some information and any risks
141
that you are identifying you want to place it here again you want to show your due diligence
142
that you know what's going on with the project
143
and anything that's going to impact your scope time and budget
144
so with this section i actually have a risk
145
and that's project timeline is being negatively impacted
146
and now this is where you you give
147
that information what is it how are you going to address it
148
and is there anything else of note
149
so why is my timeline being negatively impacted is
150
because as a project we're struggling with our IT core team
151
members to complete their tasks in the timeline associated we all have had that issue
152
but this is not about finger pointing I'm now even going into greater detail why is this happening it's not
153
because they don't care they do care it's a new project was launched
154
and what happens when something new happens it's new it's shiny it's exciting
155
and everyone is told to start working on it
156
but now they're actually the department
157
that launches new project they're pulling my team members away from me why
158
because I don't have a dedicated team 100% to this project
159
in fact they have a whole bunch of other projects my subject matter experts
160
so it's a balancing act but I'm now calling out saying
161
that their managers are pulling on them to say hey start working on this project
162
so it's now my job what i'm going to do as
163
a pm is to speak to their direct managers i'm going
164
to bring up this issue for resolution to the steering committee
165
because that's their job to remove my roadblocks
166
so i just have to make sure
167
that there's a balance of time for my team am i
168
worried about this risk at the present moment not really that's why i said green
169
but if i start talking to direct managers and steering committee and nothing happens, then my project is going to go into the red very quickly.
170
But I'm going to at least show my due diligence
171
and I'm going to show the paper trail that shows that I told everybody this.
172
Again, this update is powerful and I highly recommend that all your projects have one.
173
Now that you know how to create a project status report, it's now time for you to go to the link under this video
174
and grab your seat for my free training on the Fab Five Fundamentals of Project Management.
175
If you're here for Status Reports, I'm letting you know, go there
176
because it's going to give you some really key elements that are just going to help you be amazing at project management.
177
Don't forget to subscribe to the channel, like this video, and please share it with all the people you know.
178
It really helps us grow our community, giving you more great content.
179
I really hope you like this video and please let me know
180
if you have anything else that you would add to this, any comments you have, please put them in the comments below.
181
Until the next video, see you later.

Ngữ Cảnh & Bối Cảnh

Trong video này, người dẫn chương trình, Adriana Girdler, chia sẻ một cách chi tiết về cách xây dựng các báo cáo tình trạng dự án. Cô diễn đạt rõ ràng những điều cần bao gồm trong báo cáo để đảm bảo rằng tất cả các bên liên quan đều nắm được thông tin mới nhất về tiến độ dự án. Nội dung video cũng sẽ giúp các bạn nâng cao kỹ năng quản lý dự án của mình, từ đó cải thiện khả năng giao tiếp tiếng Anh trong môi trường làm việc.

5 Câu Nói Phổ Biến Trong Giao Tiếp Hằng Ngày

  • “Bạn có biết những gì cần bao gồm trong báo cáo tình trạng dự án không?” - Câu này mở đầu cho một cuộc thảo luận và thu hút sự chú ý.
  • “Tôi nghĩ rằng nó thực sự hữu ích.” - Được sử dụng để thể hiện ý kiến cá nhân về tần suất báo cáo.
  • “Bạn muốn gửi nó cho tất cả các bên liên quan.” - Nhấn mạnh tầm quan trọng của việc thông báo chính xác cho những người liên quan.
  • “Đây là một công cụ giao tiếp.” - Câu này cho thấy mục đích của báo cáo tình trạng dự án.
  • “Có nhiều cách bạn có thể thực hiện điều này.” - Khuyến khích sự sáng tạo và linh hoạt trong cách làm báo cáo.

Hướng Dẫn Shadowing Bước Từng Bước

Để nâng cao kỹ năng phát âm tiếng Anh chuẩn và cải thiện khả năng giao tiếp, việc thực hành shadowing tiếng Anh là cực kỳ cần thiết. Dưới đây là hướng dẫn cụ thể để bạn thực hành theo video này:

  1. Xem video nhiều lần: Bắt đầu bằng việc xem video để hiểu nội dung. Lưu ý cách Adriana nhấn mạnh các câu và từ quan trọng.
  2. Ghi âm giọng nói của bạn: Khi bạn đã có trải nghiệm nghe, hãy thử ghi âm lại giọng nói của chính mình khi nói theo từng câu.
  3. So sánh với video: Nghe lại phần ghi âm của bạn và so sánh với cách Adriana phát âm. Tìm ra những điểm khác biệt và điều chỉnh.
  4. Thực hành thường xuyên: Lặp lại quá trình này vài lần trong tuần để cải thiện số lượng và chất lượng phát âm.
  5. Tham gia cộng đồng: Cùng nhau thực hành với những người khác để có thêm phản hồi và tăng cường khả năng giao tiếp trong môi trường tiếng Anh tự nhiên.

Bằng cách này, bạn không chỉ nâng cao kỹ năng shadow speak mà còn phát triển tự tin khi giao tiếp bằng tiếng Anh trong môi trường chuyên nghiệp. Hãy thử ngay hôm nay để trở thành một người nói tiếng Anh lưu loát hơn!

Phương Pháp Shadowing Là Gì?

Shadowing là kỹ thuật học ngôn ngữ có cơ sở khoa học, ban đầu được phát triển cho chương trình đào tạo phiên dịch viên chuyên nghiệp và được phổ biến rộng rãi bởi nhà đa ngôn ngữ học Dr. Alexander Arguelles. Nguyên lý cốt lõi đơn giản nhưng cực kỳ hiệu quả: bạn nghe tiếng Anh của người bản xứ và lặp lại to ngay lập tức — như một "cái bóng" (shadow) đuổi theo người nói với độ trễ chỉ 1–2 giây. Khác với luyện ngữ pháp hay học từ vựng bị động, Shadowing buộc não bộ và cơ miệng phải đồng thời xử lý và tái tạo ngôn ngữ thực tế. Các nghiên cứu khoa học xác nhận phương pháp này cải thiện đáng kể phát âm, ngữ điệu, nhịp điệu, nối âm, kỹ năng nghe và độ lưu loát khi nói — đặc biệt hiệu quả cho người luyện IELTS Speaking và muốn giao tiếp tiếng Anh tự nhiên như người bản ngữ.