1
Welcome to Young Business Professionals.
2
I'm Felix and I hope you're all fine.
3
Today I'm presenting to you the fourth video of our APQP series.
4
In a few minutes I will explain to you the most
5
important facts to be considered in APQP phase 3 in process development phase.
6
If you are interested in increasing your automotive knowledge please feel free to subscribe to my channel
7
and like the video you may also check out our Facebook page through
8
which we would like to create a community
9
that shall support each other growing everybody's knowledge what is the
10
scope of the process development phase in this part of the project the future production process for the product is being developed.
11
In addition, this planned equipment is being procured and approved.
12
This phase is starting already in parallel to the product development phase
13
and may start theoretically from that moment at which the product design can be foreseen roughly.
14
It makes sense to think about how to assemble the product already at that time.
15
It is useful to start as early as possible in parallel to the product development phase
16
and to cooperate as close as possible with the engineering department.
17
The procurement kickoff is as well part of that process.
18
And parallel product validation tests are being performed as well.
19
That's the reason for the overlapping of the process development phase and phase for product and process validation.
20
Now let's take a more detailed look on all single working packages of APQP phase 3.
21
The following working packages are part of the process design phase.
22
Process flow and layout, process FMEA, double check of planned resources,
23
control plan and MSA plan, kick off of production equipment and definition of suppliers,
24
product and process trainings to be planned, logistic concept definition, pre-serial production,
25
and the quality gate phase three.
26
Process flow and layout.
27
It is useful to know as soon as possible if the process
28
that shall be installed into the production plant later on can
29
be installed in there without any constraint from the dimensional point of view, and if the flow of the material is reasonable.
30
A process flow plan helps to design the process and shows how the process,
31
starting from receipt of incoming materials until shipment of the finished goods from the production plan is running.
32
This is also an important input for the process FMEA and control plan.
33
It's a simple tool that helps outside people to understand the flow of the process.
34
PFMEA or Process, Failure, Mode and Effects Analysis.
35
As explained already in the previous video, we will just roughly touch this topic in here as the focus shall be on the full phase
36
and not on explaining this important activity in detail.
37
The purpose of the FMEA is to identify weak points in the process design.
38
Based on the process design measures
39
that shall increase the security to fulfill product requirements reliably the pfmea is using inputs from the design fmea
40
and is identifying potential wheel points in the production process in addition it's providing important outputs
41
that will be used in the control plan a few more important facts are
42
that the fmea should be started as early as as possible in the project from the very first sketch, if possible.
43
It is never closed except the product is going end of life.
44
And the PFMEA serves a lot of input for the control plan.
45
Double check of planned resources.
46
Before to kick off procurement of the planned equipment, it makes sense to double check the originally planned resources.
47
The project has moved forward, and eventually things have developed into a different direction than planned originally.
48
Often additional or change requirements cause design changes that are impacting potentially the process and its cycle times as well.
49
This may also result in change costs, layouts, and capacity.
50
Due to that, it makes sense to check the following things.
51
The status of the budget, the status of the calculation, a number of operators that is required for the assembly process,
52
required space in the production plan, and also the achievability of production capacities, which have been promised in the quotation to the customer originally.
53
Core plan and measurement system analysis plan.
54
The next working package we are going to take a look onto is the control plan creation and MSA plan.
55
Control plan is making sure that the production process for the product is running in a structured way.
56
The target of this tool is to prevent failures and to make sure that product requirements will be kept.
57
The control plan is receiving its inputs from the process flowchart, the drawing, the process FMEA,
58
but as well from experience of customers or the internal team.
59
Planning of required test equipments and MSA planning is about to define
60
which test equipments are required to check defined characteristics of the product.
61
Therefore, it might be useful to create a plan what equipment to be procured.
62
In addition, the MSA for these equipments needs to be planned.
63
The target of the MSA is to analyze if planned equipments are capable to identify the defined measurement value.
64
Kickoff of production equipment and supplier definition.
65
After the planning process of all production equipment, including preliminary discussions with suppliers, are closed, quotations of suppliers are being negotiated.
66
After that, it may make sense to choose the best supplier through a committee, a group of responsibles in the company,
67
to define the suppliers for tools, production equipment, gouges, and what components as well.
68
All requirements should have been exchanged and clarified with sub suppliers based on a specification sheet as detailed as possible.
69
After making the final decision, orders are being sent to the suppliers.
70
They are starting now their own APQP process and are sampling the sub component in case
71
you have nominated a board component to the customer.
72
Assembly lines or tools will be approved by the process designer of your company once they are ready.
73
It is of special importance that all requirements are defined as detailed as possible at this time.
74
Sinks that should be ready and clear are drawings for single parts, including special characteristics, specification sheets,
75
PPAP requirements for the sub suppliers, and of course also the timing expectation.
76
Product and process training plan.
77
Over the period of time in which all suppliers are working to produce the production equipment, you got time to define which trainings are required for the team in a production plant.
78
That shall be responsible to run the production line in the future.
79
It is important that all employees that will be responsible in future are being trained as detailed as possible.
80
In order to make sure that no essential part of the training is missing, it makes sense to create a training plan.
81
Who needs to be trained, when, and by whom?
82
Important trainings might be the following.
83
Training of operators with regard to assembly procedures.
84
The plant quality team needs to be trained with regard to core requirements and functions of products and special characteristics,
85
as well as the production manager.
86
Logistic concept and definition.
87
Due to the fact that during the time at
88
which the production equipment is in preparation is required to supply pre-seal demands of specific part levels to the customer,
89
it is is recommended and often mandatory to create a packaging concept.
90
This should be agreed in between logistic department of supplier and customer.
91
In some cases, the packaging concept of the pre-serial production is differing from the one for serial production,
92
as for instance, volumes are lower and sometimes empty goods for empty goods management are not yet available.
93
It makes sense to perform packaging trials as early as possible,
94
as complex products might be damaged during transport or similar.
95
Pre-serial production.
96
The start of the pre-serial production is an important milestone in phase 3 of the project.
97
Ideally, production equipment should be in the final plan already.
98
Often, the equipment is not yet finally approved, as small details need to be changed and adjusted.
99
First parts will be produced, checked and supplied.
100
Typically, quantities are not yet that high in order to slowly ramp up the production.
101
These parts are also used for production validation tests often.
102
That will be performed in phase four of the project.
103
It is recommended and often the case the project team gives a big support in this part of the phase,
104
although some points might be managed already by the future action team.
105
Quality gate phase three.
106
Once all these activities are done, the project manager has once more the pleasure to present the progress of that process phase
107
to the management and top management of the company.
108
That may then decide based on the recommendation of the project manager to release APQP phase three
109
and to move on with phase four.
110
During such a gate review, the project manager is presenting which activities have been performed and if they have been closed in time.
111
In case there are still actions unfulfilled, this is the right time and place for the manager to escalate to the top management
112
and to ask for special attention and support of the management team for specific working packages.
113
In such a case, the management team may of course also decide to not release the phase.
114
Anyhow, in case they release the phase, the team is proceeding with the activities of the next one.
115
What are important learnings of phase three?
116
I listed the following points.
117
Please try to provide as much as possible time to your
118
suppliers to give them the chance to do a proper job with producing the equipment.
119
A result of high quality requires time and resources.
120
And make sure you define the requirements for them as best as possible and in time.
121
In case orders are placed and requirements for suppliers are clear and they are capable,
122
a more relaxing phase of the project starts now until the equipment is getting ready.
123
At the end of phase 3 and the transition to phase 4,
124
high attention is required as often a lot of final changes have to be implemented under big time pressure.
125
The better the team was working in phase one and two.
126
The smoother this phase should be running now.
127
Well this was my short introduction into the process design phase.
128
Thanks to all of you for watching this video until the end.
129
I hope you enjoyed it.
130
I'm looking forward for your likes and your feedback below the video.
131
Please subscribe to the channel to not miss further APQP videos.
132
Please feel free to join our Facebook community.
133
You will find the link below the video.
134
Have a great day.

앱 다운로드

유창하게 말하는 데 필요한 모든 것

AI 발음 평가문장마다 점수 확인
IPA 발음 연습모든 소리 마스터
단어 학습나만의 단어장 만들기
단어 게임놀면서 외우기

같은 채널

FOR YOU

추천 영상

이 레슨의 어휘와 말하기 포인트

이 C1 수준 말하기 레슨은 영상 “APQP Phase 3 - Process development phase”을(를) 바탕으로 합니다. 가장 자주 반복되는 단어는 다음과 같습니다: process, phase, production, equipment, product. 이 영상에는 섀도잉할 문장 134개와 단어 1787개가 있습니다. 말하는 구간의 길이는 13:19입니다. 화자는 분당 약 134단어의 일정한 속도로 말해서 섀도잉하기에 편한 속도입니다. 단어의 88%가 영어에서 가장 많이 쓰이는 3,000단어에 속합니다. 나머지는 연습 전에 미리 확인해 두세요.

이 영상의 핵심 어휘

영상에서 가장 어려운 단어 15개를 발음, 뜻과 함께 정리했습니다.

단어발음뜻
supplier 명사/səˈplaɪə/공급자
characteristic 명사/ˌkæɹ(ə)ktəˈɹɪstɪk/특성, 특징
approve 동사/əˈpɹuːv/승인하다, 찬성하다
quotation 명사/kwoʊˈteɪʃn̩/견적
specification 명사사양, 스펙
subscribe 동사/səbˈskɹaɪb/구독하다
measurement 명사/ˈmɛʒ.ə.mənt/측정
nominate 동사/ˈnɑ.mɪ.neɪt/지명하다, 노미네이트하다
assemble 동사/əˈsɛm.bəl/모으다
calculation 명사/ˌkælkjuˈleɪʃn̩/계산
cooperate 동사/kəʊˈɒp.ə.ɹeɪt/협력하다
analyze 동사/ˈæn.əˌlaɪz/분석하다
fulfill 동사/fʊlˈfɪl/수행하다
negotiate 동사/nəˈɡəʊ.ʃi.eɪt/교섭하다
differ 동사/ˈdɪfɚ/다르다

이 영상의 문법

화자가 가장 많이 쓰는 문형을 영상 속 실제 표현과 함께 정리했습니다.

문형영상 속 표현
수동태 be + 과거분사 — 누가 하는지보다 무슨 일이 일어나는지에 초점be considered · being developed · being procured
현재완료 have/has + 과거분사 — 과거의 일이 지금도 관련이 있을 때has moved · have been promised · have nominated

주의할 발음

화자는 I'm, you're 같은 축약형과 약화된 형태를 4번 사용합니다. 들리는 대로 짧게 발음하세요.

  • “sh”와 “zh” 소리: validation /ˌvæl.əˈdeɪ.ʃən/, quotation /kwoʊˈteɪʃn̩/, measurement /ˈmɛʒ.ə.mənt/, shipment /ˈʃɪpmənt/, calculation /ˌkælkjuˈleɪʃn̩/
  • 긴 단어 — 강세 위치에 주의: validation /ˌvæl.əˈdeɪ.ʃən/, characteristic /ˌkæɹ(ə)ktəˈɹɪstɪk/, ideally /aɪˈdi.ə.li/, cooperate /kəʊˈɒp.ə.ɹeɪt/, automotive /ˌɔtəˈmoʊtɪv/

한국어 화자가 어려워하는 소리:

  • /f/ — ㅍ(/p/)으로 바꾸지 말고 윗니를 아랫입술에 대기: foresee /fɔɹˈsi/, clarify /ˈklæɹ.ɪ.faɪ/, fulfill /fʊlˈfɪl/, differ /ˈdɪfɚ/
  • /v/ — ㅂ(/b/)과 구별하기: validation /ˌvæl.əˈdeɪ.ʃən/, approve /əˈpɹuːv/, overlap /ˌəʊvəˈlæp/, automotive /ˌɔtəˈmoʊtɪv/

이 영상으로 연습하는 방법

  1. 먼저 말하지 않고 영상을 끝까지 듣고 모르는 단어를 적어 둡니다.
  2. 보통 속도로 한 문장씩 섀도잉하고, 화자의 리듬과 맞을 때까지 반복합니다.
  3. 자신의 목소리를 녹음해 원본과 비교하고, supplier, characteristic, approve 같은 단어에 특히 주의합니다.

쉐도잉이란? 영어 실력을 빠르게 키우는 과학적 방법

쉐도잉(Shadowing)은 원래 전문 통역사 훈련을 위해 개발된 언어 학습 기법으로, 다언어 학자인 Dr. Alexander Arguelles에 의해 대중화된 방법입니다. 핵심 원리는 간단하지만 매우 강력합니다: 원어민의 영어를 들으면서 1~2초의 짧은 지연으로 즉시 소리 내어 따라 말하는 것——마치 '그림자(shadow)'처럼 화자를 따라가는 것입니다. 문법 공부나 수동적인 청취와 달리, 쉐도잉은 뇌와 입 근육이 동시에 실시간으로 영어를 처리하고 재현하도록 훈련합니다. 연구에 따르면 이 방법은 발음 정확도, 억양, 리듬, 연음, 청취력, 말하기 유창성을 크게 향상시킵니다. IELTS 스피킹 준비와 자연스러운 영어 소통을 원하는 분들에게 특히 효과적입니다.

섀도잉 방법: 단계별 전체 가이드 읽기 →