Welcome to Young Business Professionals.
2
I'm Felix and I hope you are all fine today.
3
We are taking a look today on APQP Phase 4, the Product and Process Validation Phase.
4
This is already the fifth video of our APQP Playlist.
5
This video will take you on a 10 minutes tour through this project phase.
6
Make sure you're watching this until the end as we releasing
7
important lessons learned of phase four at the end of the video.
8
If you're interested in increasing your automotive knowledge, please feel to subscribe to my channel and like the video.
9
You might also check out our Facebook page through
10
which we would like to create a community that shall support each other growing everybody's knowledge.
11
What is the purpose of the product and process validation phase?
12
During that phase of the project, the pre-serial production is taking place.
13
Production equipment and board components are being released through PPAP approvals and run-it rates at sub-suppliers.
14
The pre-serial products are used for process validation tests.
15
After that, these results are shared with the customer as a part of the PPAP documentation.
16
Now, let's take a more detailed look on all single working packages that can be a part of APQB Phase 4.
17
The product and process validation phase may be splitted into the following working packages.
18
Tracking and approval of production equipment, approval of board components, process validation,
19
product trainings, finalization of quality planning,
20
approval of production and run at weights and a sampling according to PPAP
21
or EMPB standard and finally a quality gate review of phase 4.
22
Tracking and approval of production equipment.
23
The status tracking process is of course already started in phase 3 of the project
24
but it is continued in phase 4 as well.
25
Nominated suppliers are monitored frequently in order to check the timing status of the production equipment.
26
The target is to approve the equipment as soon as possible as the requirements
27
that were given in specification sheets can be proven.
28
Often a preliminary approval of the equipment is happening at the location of the supplier.
29
Later a final approval in the production plant is taking place.
30
Approval of board components.
31
In parallel a similar process will be performed for the board components.
32
Suppliers will be monitored as well.
33
The supplier APQB process is being tracked.
34
The supplier is providing the documentation on the customer as soon
35
as requirements for the components can be proven under serial production conditions.
36
For important components, a production approval and a round rate at the supplier may take place.
37
It is common that also preliminary or conditional approved components will be used for pre-serial production in this phase.
38
Process validation.
39
As soon as the product and the equipment is achieving a certain readiness, the process validation may start.
40
All tools should be approved and or at least no major changes should be performed anymore at the equipment.
41
In addition, the team that assembles the components for validation should be trained.
42
Components will be produced and provided for the test.
43
This test plan is based on the design validation plan that was defined and performed already in phase two of the project.
44
Sometimes tests can be skipped or shortened as they have been performed already in the product design phase.
45
The duration of the test is depending on the specification
46
and is the overall target to prove that the product requirements can be achieved
47
or can be reached while simulating real situation through these tests.
48
Typical tests can be temperature cycle tests, vibration tests, functional tests or durability tests.
49
To perform product trainings according to the training plan.
50
In phase 3 of the project a training plan for product and process trainings was defined.
51
Trainings for a production team such as operators or shift leaders according to created work instructions should be done.
52
As well as the logistic team should be trained according to the packaging instructions and further specifications.
53
The quality team needs to be instructed according to the control plan and the test plan.
54
Introductions into new test equipment needs to be given.
55
it's important that all team members
56
that are in touch with the product understand its main functions
57
and the drawing as well as the special characteristics of the
58
product finalization of quality planning within project phase 4 the quality planning process will be closed
59
and all planned test equipment and method will be applied
60
so procured test equipments are are being installed and first tests are being performed during the pre-seal production.
61
Short-term capability studies can be performed and a special focus on fulfillment of special characteristics should be given.
62
In addition, the measurement system analysis can be started for new test equipment.
63
The target is to check if identified error pattern can be identified correctly with procured test equipment.
64
In addition, the control plan is being finalized for the level of the serial production.
65
Approval of production and run and wait.
66
Once all adjustments of the production equipment are closed in order to reach the product requirements on a repeatable level,
67
the time of the full production approval is getting closer.
68
At this juncture, not just the cycle times of all production depths are compared versus the planned and calculated values,
69
but also it is checked if all requirements can be met.
70
If this is the case, the product can be produced at planned cost and also planned capacities,
71
which have been promised to the customer previously can be kept.
72
In order to reach the production approval, often a so-called run-at rate will be performed.
73
The run-at rate is a final trial run at which the production at serial conditions is being simulated.
74
It is recommended to perform a production trial that takes several days
75
or at least a few shifts on all new equipments in order to identify downtimes,
76
scrap, and NOK parts, as well as OK components output.
77
The result of the run-and-rate is the statement if a production approval can be declared or not.
78
Sometimes this is being performed in presence of the customer.
79
Sampling according to PPAP or EMPP.
80
Once the serial production process is installed and approved, the team can proceed with the sampling of the product.
81
This is the approval that all product requirements can be achieved permanently with the installed production process.
82
In order to reach that a bunch of documentation will be submitted to the customer.
83
The scope of this documentation package is depending on agreements that have been made before.
84
If the project has a smaller scope, typically the documentation package requires less information.
85
The sampling can be performed according to different standards such as the VDA standard or the IAG standard.
86
We will provide you further details about these different sampling levels in further videos on that channel.
87
After received up the documentation from the customer it is basically his job to provide a feedback on
88
that and this is to be done in phase 5 of the project.
89
Quality gate phase 4.
90
Once all these activities are done the project manager has the
91
pleasure to present the progress of the process phase to the management and top management of the company.
92
That may then decide, based on the recommendation of the project manager, to release APQB phase 4 and to move on with phase 5.
93
During such a gate review, the project manager is presenting which activities have been performed and if they have been closed in time.
94
In case there are still actions unfulfilled, this is the right time and place for the manager to escalate
95
that to the management and ask for special attention and support of the management team.
96
In such a case the team may of course also decide not to release the phase.
97
Anyhow in case they release the phase the team is proceeding with activities of the next one.
98
Important learnings of phase 4 are the following.
99
In general high efforts are required in order to reach the approval and sampling timing.
100
The reason therefore is typically that a lot of small adjustments need to be performed in a very short time.
101
The team can prevent these things by giving the highest possible attention within phases one and two,
102
three of the project.
103
As more efforts it's spending before, as better it is prepared for the critical phase right now.
104
The team is focused to reach a defined target date for the sampling,
105
as with approval of the sampling documentation invoices for the production equipment can be raised to the customer.
106
And of course also the sampling date is important to be kept for the customer.
107
Another important fact is that all sampling requirements should be clarified as early as possible in the project.
108
It is definitely too late to clarify them within phase 4.
109
They should be discussed and fixed already in phase 0 or 1 of the project.
110
Otherwise it may occur that massive changes of the project efforts are a result of insufficient clarification.
111
Well, that was my short video about APQP Phase 4.
112
Thanks to all of you for watching this video until the end.
113
I hope you enjoyed the video.
114
I'm looking forward for your likes and your feedback below.
115
Please subscribe to the channel to not miss further APQP updates.
116
Please feel free to join our Facebook community.
117
You will find the link below the video.
118
Have a great day.
119
you

アプリをダウンロード

流暢に話すために必要なすべて

AI発音採点文ごとに採点
IPA練習すべての音をマスター
単語学習自分の単語帳を作る
単語ゲーム遊びながら覚える

同じチャンネル

FOR YOU

おすすめ動画

このレッスンの語彙とスピーキングのポイント

このC1レベルのスピーキングレッスンは、動画「APQP Phase 4 - Product & Process validation phase」を教材にしています。 繰り返し出てくる語は次のとおりです:phase, production, test, approval, equipment。 この動画には、シャドーイング用の文が119文、単語が1562語あります。 音声の長さは11:14です。 話す速さは1分あたり約139語で安定しており、シャドーイングしやすいペースです。 単語の86%は英語の頻出3,000語に含まれます。残りは練習の前に確認しておきましょう。

この動画の重要語彙

動画の中で特に難しい単語15語を、発音と意味つきで紹介します。

単語発音意味
supplier 名詞/səˈplaɪə/サプライヤー, 供給者
approve 動詞/əˈpɹuːv/承認する, 賛成する
specification 名詞仕様, スペック
simulate 動詞/ˈsɪm.jə.lət/シミュレートする
adjustment 名詞/əˈd͡ʒʌst.mənt/調整, 調節
characteristic 名詞/ˌkæɹ(ə)ktəˈɹɪstɪk/特性, 特徴
subscribe 動詞/səbˈskɹaɪb/購読する
anyhow 副詞/ˈɛn.i.haʊ/とにかく, 何しろ
downtime 名詞/ˈdaʊnˌtaɪm/ダウンタイム
durability 名詞/dəɹəˈbɪləti/耐久性
escalate 動詞/ˈɛs.kə.leɪt/エスカレートする
invoice 名詞/ˈɪnˌvɔɪs/送り状, インボイス
shorten 動詞/ˈʃɔɹtn̩/縮める, 短くする
nominate 動詞/ˈnɑ.mɪ.neɪt/指名する, ノミネートする
vibration 名詞/vaɪˈbɹeɪʃən/振動

動画に出てくる句動詞

単語意味
check out 動詞試験する, 検査する

この動画の文法

話し手がよく使っている文型を、動画の実際の表現とともに紹介します。

文型動画での表現
受動態 be + 過去分詞 — 誰がするかより、何が起きるかに焦点を当てるbeing released · are shared · may be splitted
現在完了形 have/has + 過去分詞 — 過去の出来事が今も関係しているhave been performed · have been promised · have been made

注意したい発音

話し手はI'm, you'reなど、短縮形や弱形を4回使っています。聞こえたとおりの短い形で発音しましょう。

  • 「sh」と「zh」の音: validation /ˌvæl.əˈdeɪ.ʃən/, documentation /ˌdɑkjəmɛnˈteɪʃən/, shorten /ˈʃɔɹtn̩/, clarification /ˌklæɹɪfɪˈkeɪʃən/, vibration /vaɪˈbɹeɪʃən/
  • 長い単語(アクセントの位置に注意): validation /ˌvæl.əˈdeɪ.ʃən/, documentation /ˌdɑkjəmɛnˈteɪʃən/, characteristic /ˌkæɹ(ə)ktəˈɹɪstɪk/, durability /dəɹəˈbɪləti/, repeatable /ɹɪˈpiːtəbəl/

日本語話者が苦手な音:

  • /r/ と /l/ の区別 — /l/ は舌先を歯茎につけ、/r/ はどこにもつけない: clarify /ˈklæɹ.ɪ.faɪ/, durability /dəɹəˈbɪləti/, repeatable /ɹɪˈpiːtəbəl/, clarification /ˌklæɹɪfɪˈkeɪʃən/
  • /v/ — /b/ にならないように、上の歯を下唇に当てる: validation /ˌvæl.əˈdeɪ.ʃən/, approve /əˈpɹuːv/, invoice /ˈɪnˌvɔɪs/, vibration /vaɪˈbɹeɪʃən/, automotive /ˌɔtəˈmoʊtɪv/
  • /f/ — 「フ」ではなく、上の歯と下唇で出す: clarify /ˈklæɹ.ɪ.faɪ/, finalize /ˈfaɪ.nə.laɪz/, fulfilment /fʊlˈfɪl.mənt/, clarification /ˌklæɹɪfɪˈkeɪʃən/, insufficient /ɪnsəˈfɪʃənt/

この動画での練習方法

  1. まず声を出さずに動画を最後まで聞き、知らない単語をメモします。
  2. 通常の速度で一文ずつシャドーイングし、話し手のリズムに合うまで繰り返します。
  3. 自分の声を録音して元の音声と比べます。supplier, approve, specificationなどの単語に特に注意しましょう。

シャドーイングとは?英語上達に効果的な理由

シャドーイング(Shadowing)は、もともとプロの通訳者養成プログラムで開発された言語学習法で、多言語習得者として知られるDr. Alexander Arguelles によって広く普及されました。方法はシンプルですが非常に効果的:ネイティブスピーカーの英語を聞きながら、1〜2秒の遅延で声に出してすぐに繰り返す——まるで「影(shadow)」のように話者を追いかけます。文法ドリルや受動的なリスニングと異なり、シャドーイングは脳と口の筋肉が同時にリアルタイムで英語を処理・再現することを強制します。研究により、発音精度、抑揚、リズム、連音、リスニング力、そして会話の流暢さが大幅に向上することが確認されています。IELTSスピーキング対策や自然な英語コミュニケーションを目指す方に特におすすめです。

シャドーイングのやり方: ステップ別の完全ガイドを読む →