Welcome to Young Business Professionals.
2
I'm Felix and today I am presenting to you the third video of our APQP series.
3
In a few minutes I will explain to you the most important facts to be considered in APQP phase 1, the so-called project planning phase.
4
If you are interested in increasing your automotive knowledge please feel free to subscribe to my channel and like the video.
5
You may also check out our Facebook page through
6
which we would like to create a community that shall support each other growing everybody's knowledge.
7
What is the purpose of the APQP Phase 1 project planning?
8
After receiving the project nomination from the customer at the end of APQP Phase 0 the project planning phase is kicked off.
9
As the The name already says the purpose of this phase is mainly to plan all activities
10
and resources that will be needed in the whole project.
11
But as you can see in the phase diagram on that slide,
12
also a couple of activities from phase two are launched and running already in parallel.
13
For instance, the product design process may run already once the project is kicked off.
14
But let's start from the beginning.
15
The starting point of phase one is the project kickoff meeting.
16
This meeting is giving the official project order to the project team.
17
Typically the whole future project team and members of the management are joining these meetings.
18
The meeting is symbolizing as well the handover of the responsibility from the sales team to the project team.
19
The scope of the project will be introduced roughly to the full team.
20
The majority of the participants was already involved in the RFQ phase before
21
but in case team members are changing it makes sense to introduce the content again.
22
It's also important to define the real project targets
23
and even more important to define non-targets as pretty often project scope is adjusted during the lifetime of the project
24
and it is important to distinguish from the original target and new requirements that have been added later on.
25
During the kick-off meeting timing requirements,
26
budget requirements and the most important product and quality requirements will be introduced to the team.
27
In addition all team members will be defined and the team is cross-checking
28
if they are still open points available from the previous project phase.
29
These will be listed in order to make sure that the responsible team member may solve them within the redefined timing targets.
30
Once the meeting is closed, the project team starts to work during the first phase.
31
The majority of the activities is related to the project manager.
32
Project planning, time plan.
33
He is starting to transform the drafted time plan
34
that was already created in phase 0 into a more detailed one
35
that is considering all internal working packages that will be aligned according to internal and customer milestones.
36
All important project milestones such as the design freeze, first of two parts, availability,
37
PPAP and start of production should be considered.
38
It is useful for the project manager to analyze the time plan with regard to the critical path.
39
The critical path is a chain of working packages
40
or activities during the project
41
that in case one single step in this chain is delayed the rest of the activities inside this chain will delay accordingly.
42
So we are talking about the most sensitive activities of the project with regard to delays.
43
So this is a kind of risk analysis that may help the project manager to understand priorities during the project.
44
Project planning budget calculation.
45
Once the project plan is done,
46
it's time to review once again if major changes to the product cost calculation
47
and the project budget plan needs to be performed.
48
In the best case, there is no update that needs to be driven, but often new requirements from the customers are coming up
49
and it is important to monitor these ones in order to raise the hand asking to compensate the change cost accordingly.
50
This is a permanent activity that should be repeated in each of the project phases.
51
Quality gate phase one.
52
Once all these activities are done, the project manager has the pleasure to present the progress of the process phase to the management
53
and top management of the company.
54
That may then decide based on the recommendation of the project manager to release APQP phase one
55
and open the gate to phase two.
56
During such a gate review the project manager is presenting which activities have been performed and if they have been
57
closed in time.
58
In case there are still actions unfulfilled this is the right time and place for
59
the manager to escalate that to the management and to ask for special attention and support of the management.
60
In such a case the management team may of course also decide to not release the phase.
61
Anyhow in case they release the phase the team is proceeding with activities for the next phase.
62
Well this was my short introduction into the project planning stage.
63
Thanks to all of you for watching this video until the end.
64
I hope you enjoyed the video i'm looking forward for your likes
65
and your feedback below the video please subscribe to my channel
66
to not miss further apqb updates please feel free to join
67
our facebook community you will find the link below the video have a great day

Descargar app

Todo lo que necesitas para hablar con fluidez

Pronunciación con IAEvalúa cada oración
Práctica de IPADomina cada sonido
VocabularioConstruye tu banco de palabras
Juego de vocabularioAprende mientras juegas

Mismo canal

FOR YOU

Recomendar Video

Vocabulario y notas de pronunciación para esta lección

Esta lección de conversación de nivel C1 se basa en el vídeo “APQP Phase 1 - Project planning”. Las palabras que más se repiten: project, phase, activities, manager, planning. Este vídeo tiene 67 frases y 907 palabras para practicar shadowing. La parte hablada dura 6:18. El hablante mantiene un ritmo constante de unas 144 palabras por minuto, cómodo para el shadowing. El 90 % de las palabras está entre las 3.000 más comunes del inglés; conviene repasar el resto antes de empezar.

Vocabulario clave de este vídeo

Las 15 palabras más avanzadas del vídeo, con su pronunciación y significado:

PalabraPronunciaciónSignificado
milestone sustantivo/ˈmaɪlˌstoʊn/hito, mojón
calculation sustantivo/ˌkælkjuˈleɪʃn̩/cálculo, calculación
subscribe verbo/səbˈskɹaɪb/suscribirse, subscribirse
accordingly adverbio/əˈkɔɹ.dɪŋ.li/en consecuencia, como corresponde
escalate verbo/ˈɛs.kə.leɪt/elevar a un nivel superior
handover sustantivo/ˈhændˌoʊvɚ/traspaso
symbolize verbo/ˈsɪmbəlaɪz/simbolizar, parabolizar
unfulfilled adjetivoinsatisfecho, poco logrado
align verbo/əˈlaɪn/alinearse, alinear
participant sustantivo/pɑːɹˈtɪsəpənt/participante, partícipe
compensate verbo/ˈkɑm.pənˌseɪt/compensar
analyze verbo/ˈæn.əˌlaɪz/analizar
diagram sustantivo/ˈdaɪ.ə.ɡɹæm/diagrama
distinguish verbo/dɪˈstɪŋ.ɡwɪʃ/distinguir
automotive adjetivo/ˌɔtəˈmoʊtɪv/automotor

Phrasal verbs que vas a escuchar

PalabraSignificado
check out verboinvestigar, chequear
come up verbosalir a relucir

Gramática en este vídeo

Las estructuras que más usa el hablante, con las palabras exactas del vídeo:

EstructuraEn el vídeo
Voz pasiva be + participio pasado — importa lo que ocurre, no quién lo hacebe considered · is kicked · will be needed
Present perfect have/has + participio pasado — una acción pasada que sigue importando ahorahave been added · have been performed

Pronunciación a tener en cuenta

  • Los sonidos de “sh” y “zh”: calculation /ˌkælkjuˈleɪʃn̩/, distinguish /dɪˈstɪŋ.ɡwɪʃ/, nomination /ˌnɑmɪˈneɪʃən/, recommendation /ˌɹɛkəmɛnˈdeɪʃən/
  • Palabras largas — cuida el acento: accordingly /əˈkɔɹ.dɪŋ.li/, participant /pɑːɹˈtɪsəpənt/, automotive /ˌɔtəˈmoʊtɪv/, nomination /ˌnɑmɪˈneɪʃən/, recommendation /ˌɹɛkəmɛnˈdeɪʃən/

Sonidos difíciles para hispanohablantes:

  • /v/ — no es /b/: los dientes tocan el labio inferior: handover /ˈhændˌoʊvɚ/, automotive /ˌɔtəˈmoʊtɪv/
  • /z/ — sonora, no /s/: symbolize /ˈsɪmbəlaɪz/, analyze /ˈæn.əˌlaɪz/
  • /h/ — una aspiración suave, no la “j”: anyhow /ˈɛn.i.haʊ/, handover /ˈhændˌoʊvɚ/

Cómo practicar con este vídeo

  1. Escucha el vídeo entero una vez sin hablar y anota las palabras que no conoces.
  2. Haz shadowing frase por frase a velocidad normal, repitiendo cada una hasta que tu ritmo coincida con el del hablante.
  3. Grábate y compara con el original, prestando atención a palabras como milestone, calculation, subscribe.

¿Qué es la Técnica de Shadowing?

Shadowing es una técnica de aprendizaje de idiomas respaldada por la ciencia, desarrollada originalmente para la formación de intérpretes profesionales y popularizada por el políglota Dr. Alexander Arguelles. El método es simple pero poderoso: escuchas audio en inglés nativo y lo repites en voz alta de inmediato, como una sombra que sigue al hablante con solo 1-2 segundos de retraso. A diferencia de la escucha pasiva o los ejercicios de gramática, el shadowing obliga a tu cerebro y músculos de la boca a procesar y reproducir simultáneamente patrones de habla reales. Las investigaciones muestran que mejora significativamente la precisión de la pronunciación, la entonación, el ritmo, el habla conectada, la comprensión auditiva y la fluidez al hablar, convirtiéndola en una de las metodologías más efectivas para la preparación del IELTS Speaking y la comunicación en inglés en el mundo real.

Técnica de shadowing: lee la guía completa paso a paso →