Welcome to Young Business Professionals.
2
I'm Felix and today I am presenting to you the third video of our APQP series.
3
In a few minutes I will explain to you the most important facts to be considered in APQP phase 1, the so-called project planning phase.
4
If you are interested in increasing your automotive knowledge please feel free to subscribe to my channel and like the video.
5
You may also check out our Facebook page through
6
which we would like to create a community that shall support each other growing everybody's knowledge.
7
What is the purpose of the APQP Phase 1 project planning?
8
After receiving the project nomination from the customer at the end of APQP Phase 0 the project planning phase is kicked off.
9
As the The name already says the purpose of this phase is mainly to plan all activities
10
and resources that will be needed in the whole project.
11
But as you can see in the phase diagram on that slide,
12
also a couple of activities from phase two are launched and running already in parallel.
13
For instance, the product design process may run already once the project is kicked off.
14
But let's start from the beginning.
15
The starting point of phase one is the project kickoff meeting.
16
This meeting is giving the official project order to the project team.
17
Typically the whole future project team and members of the management are joining these meetings.
18
The meeting is symbolizing as well the handover of the responsibility from the sales team to the project team.
19
The scope of the project will be introduced roughly to the full team.
20
The majority of the participants was already involved in the RFQ phase before
21
but in case team members are changing it makes sense to introduce the content again.
22
It's also important to define the real project targets
23
and even more important to define non-targets as pretty often project scope is adjusted during the lifetime of the project
24
and it is important to distinguish from the original target and new requirements that have been added later on.
25
During the kick-off meeting timing requirements,
26
budget requirements and the most important product and quality requirements will be introduced to the team.
27
In addition all team members will be defined and the team is cross-checking
28
if they are still open points available from the previous project phase.
29
These will be listed in order to make sure that the responsible team member may solve them within the redefined timing targets.
30
Once the meeting is closed, the project team starts to work during the first phase.
31
The majority of the activities is related to the project manager.
32
Project planning, time plan.
33
He is starting to transform the drafted time plan
34
that was already created in phase 0 into a more detailed one
35
that is considering all internal working packages that will be aligned according to internal and customer milestones.
36
All important project milestones such as the design freeze, first of two parts, availability,
37
PPAP and start of production should be considered.
38
It is useful for the project manager to analyze the time plan with regard to the critical path.
39
The critical path is a chain of working packages
40
or activities during the project
41
that in case one single step in this chain is delayed the rest of the activities inside this chain will delay accordingly.
42
So we are talking about the most sensitive activities of the project with regard to delays.
43
So this is a kind of risk analysis that may help the project manager to understand priorities during the project.
44
Project planning budget calculation.
45
Once the project plan is done,
46
it's time to review once again if major changes to the product cost calculation
47
and the project budget plan needs to be performed.
48
In the best case, there is no update that needs to be driven, but often new requirements from the customers are coming up
49
and it is important to monitor these ones in order to raise the hand asking to compensate the change cost accordingly.
50
This is a permanent activity that should be repeated in each of the project phases.
51
Quality gate phase one.
52
Once all these activities are done, the project manager has the pleasure to present the progress of the process phase to the management
53
and top management of the company.
54
That may then decide based on the recommendation of the project manager to release APQP phase one
55
and open the gate to phase two.
56
During such a gate review the project manager is presenting which activities have been performed and if they have been
57
closed in time.
58
In case there are still actions unfulfilled this is the right time and place for
59
the manager to escalate that to the management and to ask for special attention and support of the management.
60
In such a case the management team may of course also decide to not release the phase.
61
Anyhow in case they release the phase the team is proceeding with activities for the next phase.
62
Well this was my short introduction into the project planning stage.
63
Thanks to all of you for watching this video until the end.
64
I hope you enjoyed the video i'm looking forward for your likes
65
and your feedback below the video please subscribe to my channel
66
to not miss further apqb updates please feel free to join
67
our facebook community you will find the link below the video have a great day

הורד אפליקציה

כל מה שאתה צריך כדי לדבר בשטף

הגיית AIציון לכל משפט
תרגול IPAשלוט בכל צליל
אוצר מיליםבנה את מאגר המילים שלך
משחק אוצר מיליםלמד תוך כדי משחק

אותו ערוץ

FOR YOU

המלץ על סרטון

אוצר מילים והערות הגייה לשיעור הזה

שיעור הדיבור הזה ברמה C1 מבוסס על הסרטון “APQP Phase 1 - Project planning”. המילים שחוזרות הכי הרבה: project, phase, activities, manager, planning. בסרטון הזה יש 67 משפטים ו-907 מילים לתרגול Shadowing. הדיבור נמשך 6:18. הדובר שומר על קצב יציב של כ-144 מילים בדקה, קצב נוח לתרגול Shadowing. 90% מהמילים נמצאות בין 3,000 המילים הנפוצות ביותר באנגלית; כדאי ללמוד את השאר לפני שמתחילים.

אוצר מילים מרכזי בסרטון הזה

12 המילים המתקדמות ביותר בסרטון, עם ההגייה והמשמעות שלהן:

מילההגייהמשמעות
milestone שם עצם/ˈmaɪlˌstoʊn/אבן מיל, אבן דרך
calculation שם עצם/ˌkælkjuˈleɪʃn̩/חִשׁוּב \ חישוב
subscribe פועל/səbˈskɹaɪb/נִמְנָה
anyhow תואר הפועל/ˈɛn.i.haʊ/בְּכָל אֹפֶן
escalate פועל/ˈɛs.kə.leɪt/הִסְלִים
participant שם עצם/pɑːɹˈtɪsəpənt/מִשׁתַתֵף
compensate פועל/ˈkɑm.pənˌseɪt/תִּגְמֵל
diagram שם עצם/ˈdaɪ.ə.ɡɹæm/תַּרְשִׁים
distinguish פועל/dɪˈstɪŋ.ɡwɪʃ/הבחין
transform פועל/tɹænsˈfɔɹm/לשנות
adjust פועל/əˈd͡ʒʌst/כוונן, התאים
recommendation שם עצם/ˌɹɛkəmɛnˈdeɪʃən/הַמְלָצָה

Phrasal verbs שתשמעו

מילהמשמעות
check out פועלבדק

דקדוק בסרטון הזה

המבנים שהדובר משתמש בהם הכי הרבה, עם המילים המדויקות מהסרטון:

מבנהבסרטון
סביל (Passive voice) be + past participle — הדגש הוא על מה שקורה, לא על מי שעושה את הפעולהbe considered · is kicked · will be needed
הווה מושלם (Present perfect) have/has + past participle — פעולה שקרתה בעבר ועדיין יש לה חשיבות או השפעה עכשיוhave been added · have been performed

הגייה ששווה לשים לב אליה

  • הצלילים של “sh” ו-“zh”: calculation /ˌkælkjuˈleɪʃn̩/, distinguish /dɪˈstɪŋ.ɡwɪʃ/, nomination /ˌnɑmɪˈneɪʃən/, recommendation /ˌɹɛkəmɛnˈdeɪʃən/
  • מילים ארוכות — שימו לב להטעמה: accordingly /əˈkɔɹ.dɪŋ.li/, participant /pɑːɹˈtɪsəpənt/, automotive /ˌɔtəˈmoʊtɪv/, nomination /ˌnɑmɪˈneɪʃən/, recommendation /ˌɹɛkəmɛnˈdeɪʃən/

צלילים שדוברי עברית מתקשים בהם:

  • /æ/ — פתוח יותר מה-“אֶ” העברית, לא כמו “a” ב-“cup”: calculation /ˌkælkjuˈleɪʃn̩/, handover /ˈhændˌoʊvɚ/, analyze /ˈæn.əˌlaɪz/, diagram /ˈdaɪ.ə.ɡɹæm/, transform /tɹænsˈfɔɹm/
  • /r/ — הלשון לא נוגעת בשום מקום, לא ה-“ר” הגרונית: subscribe /səbˈskɹaɪb/, accordingly /əˈkɔɹ.dɪŋ.li/, participant /pɑːɹˈtɪsəpənt/, diagram /ˈdaɪ.ə.ɡɹæm/, transform /tɹænsˈfɔɹm/
  • עיצור קולי בסוף מילה — /b/, /d/, /g/, /z/, /v/ בלי להפוך אותם לאטומים: subscribe /səbˈskɹaɪb/, symbolize /ˈsɪmbəlaɪz/, analyze /ˈæn.əˌlaɪz/, automotive /ˌɔtəˈmoʊtɪv/

איך לתרגל עם הסרטון הזה

  1. הקשיבו לכל הסרטון פעם אחת בלי לדבר, ורשמו את המילים שאתם לא מכירים.
  2. תרגלו Shadowing משפט אחר משפט במהירות רגילה, וחזרו על כל משפט עד שהקצב שלכם תואם את הדובר.
  3. הקליטו את עצמכם והשוו למקור, תוך תשומת לב למילים כמו milestone, calculation, subscribe.

מהי טכניקת השאדואינג?

שאדואינג היא טכניקת למידת שפה מבוססת מדע שפותחה במקור להכשרת מתורגמנים מקצועיים ופופולרית על ידי הפוליגלוט ד"ר אלכסנדר ארגואלס. השיטה פשוטה אך עוצמתית: אתה מקשיב לאודיו באנגלית ילידית וחוזר עליו בקול רם מיד — כמו צל העוקב אחרי הדובר עם עיכוב של 1–2 שניות בלבד. בניגוד להאזנה פסיבית או תרגילי דקדוק, שאדואינג מכריח את המוח והשרירים בפה לעבד ולשחזר דפוסי דיבור אמיתיים בו זמנית. מחקרים מראים שזה משפר משמעותית את דיוק ההגייה, האינטונציה, הקצב, הדיבור המחובר, הבנת השמיעה ושטף הדיבור — מה שהופך אותו לאחת השיטות היעילות ביותר להכנה לIELTS Speaking ולתקשורת באנגלית בעולם האמיתי.

טכניקת Shadowing: קרא את המדריך המלא שלב אחר שלב →