Welcome to Young Business Professionals.
2
I'm Felix and today I am presenting to you the third video of our APQP series.
3
In a few minutes I will explain to you the most important facts to be considered in APQP phase 1, the so-called project planning phase.
4
If you are interested in increasing your automotive knowledge please feel free to subscribe to my channel and like the video.
5
You may also check out our Facebook page through
6
which we would like to create a community that shall support each other growing everybody's knowledge.
7
What is the purpose of the APQP Phase 1 project planning?
8
After receiving the project nomination from the customer at the end of APQP Phase 0 the project planning phase is kicked off.
9
As the The name already says the purpose of this phase is mainly to plan all activities
10
and resources that will be needed in the whole project.
11
But as you can see in the phase diagram on that slide,
12
also a couple of activities from phase two are launched and running already in parallel.
13
For instance, the product design process may run already once the project is kicked off.
14
But let's start from the beginning.
15
The starting point of phase one is the project kickoff meeting.
16
This meeting is giving the official project order to the project team.
17
Typically the whole future project team and members of the management are joining these meetings.
18
The meeting is symbolizing as well the handover of the responsibility from the sales team to the project team.
19
The scope of the project will be introduced roughly to the full team.
20
The majority of the participants was already involved in the RFQ phase before
21
but in case team members are changing it makes sense to introduce the content again.
22
It's also important to define the real project targets
23
and even more important to define non-targets as pretty often project scope is adjusted during the lifetime of the project
24
and it is important to distinguish from the original target and new requirements that have been added later on.
25
During the kick-off meeting timing requirements,
26
budget requirements and the most important product and quality requirements will be introduced to the team.
27
In addition all team members will be defined and the team is cross-checking
28
if they are still open points available from the previous project phase.
29
These will be listed in order to make sure that the responsible team member may solve them within the redefined timing targets.
30
Once the meeting is closed, the project team starts to work during the first phase.
31
The majority of the activities is related to the project manager.
32
Project planning, time plan.
33
He is starting to transform the drafted time plan
34
that was already created in phase 0 into a more detailed one
35
that is considering all internal working packages that will be aligned according to internal and customer milestones.
36
All important project milestones such as the design freeze, first of two parts, availability,
37
PPAP and start of production should be considered.
38
It is useful for the project manager to analyze the time plan with regard to the critical path.
39
The critical path is a chain of working packages
40
or activities during the project
41
that in case one single step in this chain is delayed the rest of the activities inside this chain will delay accordingly.
42
So we are talking about the most sensitive activities of the project with regard to delays.
43
So this is a kind of risk analysis that may help the project manager to understand priorities during the project.
44
Project planning budget calculation.
45
Once the project plan is done,
46
it's time to review once again if major changes to the product cost calculation
47
and the project budget plan needs to be performed.
48
In the best case, there is no update that needs to be driven, but often new requirements from the customers are coming up
49
and it is important to monitor these ones in order to raise the hand asking to compensate the change cost accordingly.
50
This is a permanent activity that should be repeated in each of the project phases.
51
Quality gate phase one.
52
Once all these activities are done, the project manager has the pleasure to present the progress of the process phase to the management
53
and top management of the company.
54
That may then decide based on the recommendation of the project manager to release APQP phase one
55
and open the gate to phase two.
56
During such a gate review the project manager is presenting which activities have been performed and if they have been
57
closed in time.
58
In case there are still actions unfulfilled this is the right time and place for
59
the manager to escalate that to the management and to ask for special attention and support of the management.
60
In such a case the management team may of course also decide to not release the phase.
61
Anyhow in case they release the phase the team is proceeding with activities for the next phase.
62
Well this was my short introduction into the project planning stage.
63
Thanks to all of you for watching this video until the end.
64
I hope you enjoyed the video i'm looking forward for your likes
65
and your feedback below the video please subscribe to my channel
66
to not miss further apqb updates please feel free to join
67
our facebook community you will find the link below the video have a great day

Télécharger l'application

Tout pour parler couramment

Prononciation IAChaque phrase notée
Phonétique (IPA)Maîtrisez chaque son
VocabulaireEnrichissez votre lexique
Jeu de vocabulaireApprenez en jouant

Même chaîne

FOR YOU

Vidéo recommandée

Vocabulaire et conseils d’expression pour cette leçon

Cette leçon d’expression orale de niveau C1 s’appuie sur la vidéo « APQP Phase 1 - Project planning ». Les mots qui reviennent le plus souvent : project, phase, activities, manager, planning. Cette vidéo contient 67 phrases et 907 mots à répéter en shadowing. La partie parlée dure 6:18. Le locuteur parle à un rythme régulier d’environ 144 mots par minute, confortable pour le shadowing. 90 % des mots font partie des 3 000 mots les plus courants en anglais ; le reste mérite d’être vu avant de commencer.

Vocabulaire clé de cette vidéo

Les 15 mots les plus avancés de la vidéo, avec leur prononciation et leur sens :

MotPrononciationSens
milestone nom/ˈmaɪlˌstoʊn/borne, borne kilométrique
calculation nom/ˌkælkjuˈleɪʃn̩/calcul
subscribe verbe/səbˈskɹaɪb/abonner, s'abonner
accordingly adverbe/əˈkɔɹ.dɪŋ.li/en conséquence, conséquemment
anyhow adverbe/ˈɛn.i.haʊ/de toute manière, de toute façon
escalate verbe/ˈɛs.kə.leɪt/intensifier
handover nom/ˈhændˌoʊvɚ/passation, rétrocession
redefine verberedéfinir
symbolize verbe/ˈsɪmbəlaɪz/symboliser
align verbe/əˈlaɪn/aligner
participant nom/pɑːɹˈtɪsəpənt/participant, participante
compensate verbe/ˈkɑm.pənˌseɪt/compenser
analyze verbe/ˈæn.əˌlaɪz/analyser
diagram nom/ˈdaɪ.ə.ɡɹæm/diagramme, schéma
distinguish verbe/dɪˈstɪŋ.ɡwɪʃ/distinguer

Les verbes à particule que vous entendrez

MotSens
check out verbemater, regarder
come up verbese montrer, sortir du bois

La grammaire de cette vidéo

Les structures que le locuteur utilise le plus, avec les mots exacts de la vidéo :

StructureDans la vidéo
Voix passive be + participe passé — l’accent est mis sur ce qui arrive, pas sur qui le faitbe considered · is kicked · will be needed
Present perfect have/has + participe passé — une action passée qui compte encore maintenanthave been added · have been performed

Prononciation à surveiller

  • Les sons « sh » et « zh »: calculation /ˌkælkjuˈleɪʃn̩/, distinguish /dɪˈstɪŋ.ɡwɪʃ/, nomination /ˌnɑmɪˈneɪʃən/, recommendation /ˌɹɛkəmɛnˈdeɪʃən/
  • Mots longs — placez bien l’accent: accordingly /əˈkɔɹ.dɪŋ.li/, participant /pɑːɹˈtɪsəpənt/, automotive /ˌɔtəˈmoʊtɪv/, nomination /ˌnɑmɪˈneɪʃən/, recommendation /ˌɹɛkəmɛnˈdeɪʃən/

Les sons difficiles pour les francophones :

  • /h/ — il se souffle, il n’est pas muet: anyhow /ˈɛn.i.haʊ/, handover /ˈhændˌoʊvɚ/
  • /r/ anglais — langue recourbée, sans frotter la gorge: subscribe /səbˈskɹaɪb/, accordingly /əˈkɔɹ.dɪŋ.li/, participant /pɑːɹˈtɪsəpənt/, diagram /ˈdaɪ.ə.ɡɹæm/, transform /tɹænsˈfɔɹm/

Comment s’entraîner avec cette vidéo

  1. Écoutez la vidéo en entier une fois sans parler et notez les mots que vous ne connaissez pas.
  2. Répétez phrase par phrase à vitesse normale, en reprenant chacune jusqu’à ce que votre rythme corresponde à celui du locuteur.
  3. Enregistrez-vous et comparez avec l’original, en faisant attention à des mots comme milestone, calculation, subscribe.

Qu'est-ce que la technique du Shadowing ?

Le Shadowing est une technique d'apprentissage des langues fondée sur la science, développée à l'origine pour la formation des interprètes professionnels. Le principe est simple mais puissant : vous écoutez de l'anglais natif et le répétez immédiatement à voix haute — comme une ombre suivant le locuteur avec un décalage de 1 à 2 secondes. Les recherches montrent une amélioration significative de la précision de la prononciation, de l'intonation, du rythme, des liaisons, de la compréhension orale et de la fluidité.

Technique du shadowing : lire le guide complet étape par étape →