Welcome to Young Business Professionals.
2
I'm Felix and today I am presenting to you the third video of our APQP series.
3
In a few minutes I will explain to you the most important facts to be considered in APQP phase 1, the so-called project planning phase.
4
If you are interested in increasing your automotive knowledge please feel free to subscribe to my channel and like the video.
5
You may also check out our Facebook page through
6
which we would like to create a community that shall support each other growing everybody's knowledge.
7
What is the purpose of the APQP Phase 1 project planning?
8
After receiving the project nomination from the customer at the end of APQP Phase 0 the project planning phase is kicked off.
9
As the The name already says the purpose of this phase is mainly to plan all activities
10
and resources that will be needed in the whole project.
11
But as you can see in the phase diagram on that slide,
12
also a couple of activities from phase two are launched and running already in parallel.
13
For instance, the product design process may run already once the project is kicked off.
14
But let's start from the beginning.
15
The starting point of phase one is the project kickoff meeting.
16
This meeting is giving the official project order to the project team.
17
Typically the whole future project team and members of the management are joining these meetings.
18
The meeting is symbolizing as well the handover of the responsibility from the sales team to the project team.
19
The scope of the project will be introduced roughly to the full team.
20
The majority of the participants was already involved in the RFQ phase before
21
but in case team members are changing it makes sense to introduce the content again.
22
It's also important to define the real project targets
23
and even more important to define non-targets as pretty often project scope is adjusted during the lifetime of the project
24
and it is important to distinguish from the original target and new requirements that have been added later on.
25
During the kick-off meeting timing requirements,
26
budget requirements and the most important product and quality requirements will be introduced to the team.
27
In addition all team members will be defined and the team is cross-checking
28
if they are still open points available from the previous project phase.
29
These will be listed in order to make sure that the responsible team member may solve them within the redefined timing targets.
30
Once the meeting is closed, the project team starts to work during the first phase.
31
The majority of the activities is related to the project manager.
32
Project planning, time plan.
33
He is starting to transform the drafted time plan
34
that was already created in phase 0 into a more detailed one
35
that is considering all internal working packages that will be aligned according to internal and customer milestones.
36
All important project milestones such as the design freeze, first of two parts, availability,
37
PPAP and start of production should be considered.
38
It is useful for the project manager to analyze the time plan with regard to the critical path.
39
The critical path is a chain of working packages
40
or activities during the project
41
that in case one single step in this chain is delayed the rest of the activities inside this chain will delay accordingly.
42
So we are talking about the most sensitive activities of the project with regard to delays.
43
So this is a kind of risk analysis that may help the project manager to understand priorities during the project.
44
Project planning budget calculation.
45
Once the project plan is done,
46
it's time to review once again if major changes to the product cost calculation
47
and the project budget plan needs to be performed.
48
In the best case, there is no update that needs to be driven, but often new requirements from the customers are coming up
49
and it is important to monitor these ones in order to raise the hand asking to compensate the change cost accordingly.
50
This is a permanent activity that should be repeated in each of the project phases.
51
Quality gate phase one.
52
Once all these activities are done, the project manager has the pleasure to present the progress of the process phase to the management
53
and top management of the company.
54
That may then decide based on the recommendation of the project manager to release APQP phase one
55
and open the gate to phase two.
56
During such a gate review the project manager is presenting which activities have been performed and if they have been
57
closed in time.
58
In case there are still actions unfulfilled this is the right time and place for
59
the manager to escalate that to the management and to ask for special attention and support of the management.
60
In such a case the management team may of course also decide to not release the phase.
61
Anyhow in case they release the phase the team is proceeding with activities for the next phase.
62
Well this was my short introduction into the project planning stage.
63
Thanks to all of you for watching this video until the end.
64
I hope you enjoyed the video i'm looking forward for your likes
65
and your feedback below the video please subscribe to my channel
66
to not miss further apqb updates please feel free to join
67
our facebook community you will find the link below the video have a great day

Скачать приложение

Всё для свободной речи

ИИ-оценка произношенияОценка каждой фразы
Практика IPAОсвойте каждый звук
СловарьСоберите свой словарный запас
Игра со словамиУчитесь играя

Тот же канал

FOR YOU

Рекомендуемое видео

Лексика и советы по произношению к этому уроку

Этот урок разговорной практики уровня C1 построен на видео «APQP Phase 1 - Project planning». Чаще всего повторяются слова: project, phase, activities, manager, planning. В этом видео 67 предложений и 907 слов для шедоуинга. Речь длится 6:18. Говорящий держит ровный темп — около 144 слов в минуту, удобный для шедоуинга. 90% слов входят в 3000 самых частых слов английского языка; остальные стоит разобрать перед занятием.

Ключевая лексика этого видео

Самые сложные слова из видео (15), с произношением и значением:

СловоПроизношениеЗначение
milestone существительное/ˈmaɪlˌstoʊn/ми́льный ка́мень, километро́вый столб
calculation существительное/ˌkælkjuˈleɪʃn̩/вычисле́ние, исчисле́ние
subscribe глагол/səbˈskɹaɪb/подпи́сывать, подписа́ть
accordingly наречие/əˈkɔɹ.dɪŋ.li/соотве́тственно
anyhow наречие/ˈɛn.i.haʊ/так и́ли ина́че
escalate глагол/ˈɛs.kə.leɪt/обостря́ть, углубля́ть
handover существительное/ˈhændˌoʊvɚ/переда́ча
redefine глаголпереопределя́ть, переопредели́ть
symbolize глагол/ˈsɪmbəlaɪz/символизи́ровать
unfulfilled прилагательноеневы́полненный
align глагол/əˈlaɪn/равня́ться, стро́иться
participant существительное/pɑːɹˈtɪsəpənt/уча́стник, уча́стница
compensate глагол/ˈkɑm.pənˌseɪt/компенси́ровать, возмеща́ть
analyze глагол/ˈæn.əˌlaɪz/анализи́ровать, проанализи́ровать
diagram существительное/ˈdaɪ.ə.ɡɹæm/план, диагра́мма

Фразовые глаголы, которые вы услышите

СловоЗначение
check out глаголпроверя́ть, прове́рить
come up глаголподнима́ться, подня́ться

Грамматика в этом видео

Конструкции, которые говорящий использует чаще всего, с точными словами из видео:

КонструкцияВ видео
Пассивный залог be + причастие прошедшего времени — важно, что происходит, а не кто это делаетbe considered · is kicked · will be needed
Present Perfect have/has + причастие прошедшего времени — прошлое действие, важное сейчасhave been added · have been performed

Произношение, на которое стоит обратить внимание

  • Звуки «sh» и «zh»: calculation /ˌkælkjuˈleɪʃn̩/, distinguish /dɪˈstɪŋ.ɡwɪʃ/, nomination /ˌnɑmɪˈneɪʃən/, recommendation /ˌɹɛkəmɛnˈdeɪʃən/
  • Длинные слова — следите за ударением: accordingly /əˈkɔɹ.dɪŋ.li/, participant /pɑːɹˈtɪsəpənt/, automotive /ˌɔtəˈmoʊtɪv/, nomination /ˌnɑmɪˈneɪʃən/, recommendation /ˌɹɛkəmɛnˈdeɪʃən/

Звуки, трудные для русскоязычных:

  • /h/ — лёгкий выдох, а не русское «х»: anyhow /ˈɛn.i.haʊ/, handover /ˈhændˌoʊvɚ/
  • Звонкие согласные в конце слова — не оглушайте их: subscribe /səbˈskɹaɪb/, symbolize /ˈsɪmbəlaɪz/, analyze /ˈæn.əˌlaɪz/, automotive /ˌɔtəˈmoʊtɪv/

Как заниматься с этим видео

  1. Прослушайте всё видео один раз молча и выпишите незнакомые слова.
  2. Повторяйте предложение за предложением на обычной скорости, пока ваш ритм не совпадёт с ритмом говорящего.
  3. Запишите себя и сравните с оригиналом, обращая внимание на такие слова, как milestone, calculation, subscribe.

Что такое техника Shadowing?

Shadowing — это научно обоснованная техника изучения языка, изначально разработанная для подготовки профессиональных переводчиков и популяризированная полиглотом доктором Александром Аргуэльесом. Метод прост, но эффективен: вы слушаете аудио на английском от носителей языка и немедленно повторяете вслух — как тень, следующая за говорящим с задержкой в 1–2 секунды. В отличие от пассивного прослушивания или грамматических упражнений, Shadowing заставляет мозг и мышцы рта одновременно обрабатывать и воспроизводить реальные речевые паттерны. Исследования показывают, что это значительно улучшает точность произношения, интонацию, ритм, связную речь, понимание на слух и беглость речи — что делает его одним из самых эффективных методов для подготовки к IELTS Speaking и реального общения на английском.

Техника шедоуинга: читать полное пошаговое руководство →