Welcome to Young Business Professionals.
2
I'm Felix and today I am presenting to you the third video of our APQP series.
3
In a few minutes I will explain to you the most important facts to be considered in APQP phase 1, the so-called project planning phase.
4
If you are interested in increasing your automotive knowledge please feel free to subscribe to my channel and like the video.
5
You may also check out our Facebook page through
6
which we would like to create a community that shall support each other growing everybody's knowledge.
7
What is the purpose of the APQP Phase 1 project planning?
8
After receiving the project nomination from the customer at the end of APQP Phase 0 the project planning phase is kicked off.
9
As the The name already says the purpose of this phase is mainly to plan all activities
10
and resources that will be needed in the whole project.
11
But as you can see in the phase diagram on that slide,
12
also a couple of activities from phase two are launched and running already in parallel.
13
For instance, the product design process may run already once the project is kicked off.
14
But let's start from the beginning.
15
The starting point of phase one is the project kickoff meeting.
16
This meeting is giving the official project order to the project team.
17
Typically the whole future project team and members of the management are joining these meetings.
18
The meeting is symbolizing as well the handover of the responsibility from the sales team to the project team.
19
The scope of the project will be introduced roughly to the full team.
20
The majority of the participants was already involved in the RFQ phase before
21
but in case team members are changing it makes sense to introduce the content again.
22
It's also important to define the real project targets
23
and even more important to define non-targets as pretty often project scope is adjusted during the lifetime of the project
24
and it is important to distinguish from the original target and new requirements that have been added later on.
25
During the kick-off meeting timing requirements,
26
budget requirements and the most important product and quality requirements will be introduced to the team.
27
In addition all team members will be defined and the team is cross-checking
28
if they are still open points available from the previous project phase.
29
These will be listed in order to make sure that the responsible team member may solve them within the redefined timing targets.
30
Once the meeting is closed, the project team starts to work during the first phase.
31
The majority of the activities is related to the project manager.
32
Project planning, time plan.
33
He is starting to transform the drafted time plan
34
that was already created in phase 0 into a more detailed one
35
that is considering all internal working packages that will be aligned according to internal and customer milestones.
36
All important project milestones such as the design freeze, first of two parts, availability,
37
PPAP and start of production should be considered.
38
It is useful for the project manager to analyze the time plan with regard to the critical path.
39
The critical path is a chain of working packages
40
or activities during the project
41
that in case one single step in this chain is delayed the rest of the activities inside this chain will delay accordingly.
42
So we are talking about the most sensitive activities of the project with regard to delays.
43
So this is a kind of risk analysis that may help the project manager to understand priorities during the project.
44
Project planning budget calculation.
45
Once the project plan is done,
46
it's time to review once again if major changes to the product cost calculation
47
and the project budget plan needs to be performed.
48
In the best case, there is no update that needs to be driven, but often new requirements from the customers are coming up
49
and it is important to monitor these ones in order to raise the hand asking to compensate the change cost accordingly.
50
This is a permanent activity that should be repeated in each of the project phases.
51
Quality gate phase one.
52
Once all these activities are done, the project manager has the pleasure to present the progress of the process phase to the management
53
and top management of the company.
54
That may then decide based on the recommendation of the project manager to release APQP phase one
55
and open the gate to phase two.
56
During such a gate review the project manager is presenting which activities have been performed and if they have been
57
closed in time.
58
In case there are still actions unfulfilled this is the right time and place for
59
the manager to escalate that to the management and to ask for special attention and support of the management.
60
In such a case the management team may of course also decide to not release the phase.
61
Anyhow in case they release the phase the team is proceeding with activities for the next phase.
62
Well this was my short introduction into the project planning stage.
63
Thanks to all of you for watching this video until the end.
64
I hope you enjoyed the video i'm looking forward for your likes
65
and your feedback below the video please subscribe to my channel
66
to not miss further apqb updates please feel free to join
67
our facebook community you will find the link below the video have a great day

Uygulamayı İndir

Akıcı konuşmak için ihtiyacınız olan her şey

AI TelaffuzHer cümleyi puanla
IPA AlıştırmasıHer sesi ustalaştır
Kelime BilgisiKelime bankanızı oluşturun
Kelime OyunuOynarken öğrenin

Aynı Kanal

FOR YOU

Video Öner

Bu dersin kelimeleri ve konuşma notları

Bu C1 seviyesindeki konuşma dersi “APQP Phase 1 - Project planning” videosuna dayanıyor. En çok tekrarlanan kelimeler: project, phase, activities, manager, planning. Bu videoda gölgeleme çalışması için 67 cümle ve 907 kelime var. Konuşma bölümü 6:18 sürüyor. Konuşmacı dakikada yaklaşık 144 kelimelik dengeli bir hızla konuşuyor; gölgeleme için rahat bir tempo. Kelimelerin %90’i İngilizcede en sık kullanılan 3.000 kelime arasında; geri kalanına başlamadan önce bakmakta fayda var.

Bu videodaki önemli kelimeler

Videodaki en ileri düzey 11 kelime, telaffuzu ve anlamıyla:

KelimeTelaffuzAnlam
milestone isim/ˈmaɪlˌstoʊn/kilometre taşı
calculation isim/ˌkælkjuˈleɪʃn̩/hesaplama
subscribe fiil/səbˈskɹaɪb/abone olmak
escalate fiil/ˈɛs.kə.leɪt/yoğunlaştırmak
handover isim/ˈhændˌoʊvɚ/devir teslim
align fiil/əˈlaɪn/hizalanmak, hizaya geçmek
participant isim/pɑːɹˈtɪsəpənt/katılımcı, iştirakçı
compensate fiil/ˈkɑm.pənˌseɪt/zararını karşılamak (indemnify), hakkını vermek
diagram isim/ˈdaɪ.ə.ɡɹæm/şema
distinguish fiil/dɪˈstɪŋ.ɡwɪʃ/ayırt etmek, ayırmak
recommendation isim/ˌɹɛkəmɛnˈdeɪʃən/tavsiye

Duyacağınız deyimsel fiiller

KelimeAnlam
check out fiilgözden geçirmek

Bu videodaki dil bilgisi

Konuşmacının en çok kullandığı yapılar, videodaki sözcüklerin aynısıyla:

YapıVideoda
Edilgen yapı be + fiilin üçüncü hâli — kimin yaptığı değil, ne olduğu önemlibe considered · is kicked · will be needed
Present perfect have/has + fiilin üçüncü hâli — geçmişte olan ama şimdi de önemli olan bir eylemhave been added · have been performed

Dikkat edilecek telaffuzlar

  • “sh” ve “zh” sesleri: calculation /ˌkælkjuˈleɪʃn̩/, distinguish /dɪˈstɪŋ.ɡwɪʃ/, nomination /ˌnɑmɪˈneɪʃən/, recommendation /ˌɹɛkəmɛnˈdeɪʃən/
  • Uzun kelimeler — vurguyu doğru yere koyun: accordingly /əˈkɔɹ.dɪŋ.li/, participant /pɑːɹˈtɪsəpənt/, automotive /ˌɔtəˈmoʊtɪv/, nomination /ˌnɑmɪˈneɪʃən/, recommendation /ˌɹɛkəmɛnˈdeɪʃən/

Türkçe konuşanların zorlandığı sesler:

  • /æ/ — “e”den daha açık: calculation /ˌkælkjuˈleɪʃn̩/, handover /ˈhændˌoʊvɚ/, analyze /ˈæn.əˌlaɪz/, diagram /ˈdaɪ.ə.ɡɹæm/, transform /tɹænsˈfɔɹm/

Bu videoyla nasıl çalışılır

  1. Videonun tamamını konuşmadan bir kez dinleyin ve bilmediğiniz kelimeleri not edin.
  2. Normal hızda cümle cümle tekrar edin; ritminiz konuşmacıyla aynı olana kadar her cümleyi yineleyin.
  3. Kendinizi kaydedin ve orijinaliyle karşılaştırın; milestone, calculation, subscribe gibi kelimelere özellikle dikkat edin.

Gölgeleme Tekniği Nedir?

Gölgeleme, başlangıçta profesyonel tercüman eğitimi için geliştirilen ve çok dilli Dr. Alexander Arguelles tarafından popüler hale getirilen, bilim destekli bir dil öğrenme tekniğidir. Yöntem basit ama güçlüdür: ana dili İngilizce olan bir sesi dinler ve hemen yüksek sesle tekrar edersiniz — konuşmacıyı 1-2 saniye gecikmeyle takip eden bir gölge gibi. Pasif dinleme veya dilbilgisi alıştırmalarının aksine, gölgeleme beyninizi ve ağız kaslarınızı gerçek konuşma kalıplarını eşzamanlı olarak işlemeye ve yeniden üretmeye zorlar. Araştırmalar, telaffuz doğruluğu, tonlama, ritim, bağlı konuşma, dinleme anlama ve konuşma akıcılığını önemli ölçüde geliştirdiğini göstermektedir — bu da onu IELTS Konuşma hazırlığı ve gerçek dünya İngilizce iletişimi için en etkili yöntemlerden biri yapar.

Shadowing tekniği: adım adım eksiksiz rehberi okuyun →